1 / 11 / 2013

yrekazzyzxamuckInternet and Web Development

Dec 4, 2013 (3 years and 6 months ago)

79 views

1 / 11 /
2013

Task Name

Duration

Start

Finish

Iteration 2 : User Experience (Preperation for Acceptance)

14 days

Fri 18/10/13

Wed 6/11/13


Update Team
-
wiki

2 days

Fri 18/10/13

Mon 21/10/13


Use case and sequence Design for Map
-
Feature

0.5 days

Fri 18/10/13

Fri 18/10/13


Creating
Protoype

interface: "Map
-
Page"

0.5 days

Fri 18/10/13

Fri 18/10/13


Analysis on how we can allow user to declare their school actively

1 day

Fri 18/10/13

Mon 21/10/13


Development of Map Feature showing different school location base on type of
education level

4 days

Mon 21/10/13

Thu 24/10/13


Creating Acceptance Content

3 days

Tue 22/10/13

Thu 24/10/13


Adjust Codes to support school value

2 days

Tue 22/10/13

Wed 23/10/13


Creation of test
-
case Map function

1 day

Thu 24/10/13

Thu 24/10/13


Testing of Map Function

1 day

Fri 25/10/13

Fri 25/10/13


Proposal Submission

1 day

Mon 28/10/13

Mon 28/10/13


Debugging phase for Map Function

1 day

Mon 28/10/13

Mon 28/10/13


Request for Deployment of current task from client

1 day

Tue 29/10/13

Tue 29/10/13


Review and Revise Progress for Acceptance with
Supervisor ( Not Approved )

1 day

Wed 30/10/13

Wed 30/10/13


Ammend

Contents base on feedback

1 day

Thu 31/10/13

Thu 31/10/13


Rehersals

for Acceptance

1 day

Mon 4/11/13

Mon 4/11/13


Buffer

1 day

Tue 5/11/13

Tue 5/11/13


Acceptance

1 day

Wed 6/11/13

Wed 6/11/13

27/10


4 days 7/2 = 3.5
sm


xx/11

1 days 8/1 = 8
sm


xx/11


1 days 7/1 = 7
sm


xx/11


12days 12/4 = 3
sm


SI > 1.3

Very behind schedule. PM to
conduct review to determine
the cause of delay and to
reschedule project. Consider
dropping functionalities.

Hard Deadlines

Hard Deadlines


Step Up.

Make up with lost time

Make Faster Progress

Eat into Iteration Halt:

Catch up with slow progress .

Ideally : Delays will be buffered across next.

Dec Break

-
EVERYDAY ( 8hrs ) 6
-
7 days

2 weeks ( w/o
wc

. F.
es

, even more )


-
Schedule has be generously crafted to

MONDAY


Everything must be UP


WIKI


POWERPOINT FOR ACCEPTANCE


MAP FEATURE / Registration


-

This has not taken in account of Ranking.


Deployment . ( Mon Night Latest )



Must : X


Factor ( Iterative Deployment )


Don’t deliver , suggest team struggle in the beginning stage


Expect Greater Struggles

»

Is Team Ready?


Real time estimate



Competency level of individual .


Java Script


Angular JS


Bootstrap


Enforce Pair programming.


Physical collaboration for knowledge sharing.


Updating of Metrics.



Theme is
Project Management