CONSTRUCTION WEEKLY REPORT

reelingripebeltUrban and Civil

Nov 15, 2013 (3 years and 8 months ago)

97 views



CONSTRUCTION WEEKLY REPORT

NOVEMBER 2010



CONSTRUCTION

WEEKLY REPORT 01
st

NOVEMBER


7
th

NOVEMBER 2010




PROGRESS REPORT :



UNDERPASS KM 204




MINE SITE :


GENERATOR HOUSE


FUEL STORAGE




PORT :


CRUSHING PLANT


WEIGHT BRIDGE


BARGE LOADING CONVEYOR


WORKSHOP AND OFFICE


GENERATOR HOUSE


OFFICE AND MESS


SECURITY POS






CONTENTS



UNDERPASS PROGRESS AS BELOW :



The currently of progress are 96.59% :



Making sloping of retaining wall in both side direction to Port
>
Still in progress


Install open drainage hauling road under the underpass direction to port and direction to Pit
>

Still in the progress


Repair and maintenance of hauling road before and after the concrete rigid
>
Continue


Install retaining wall in both side direction to port and direction to Pit
> Still in progress

























Extra concrete wall


Lean Concrete bench in step 1






































CONSTRUCTION



UNDERPASS PROGRESS PICTURES :

























NOTE :

-

RETAINING WALL STEP 2 DIRECTION TO PORT





-

CONSTRUCT OF OPEN DRAINAGE





-

EXTRA CONCRETE WALL IN THE CRITICAL SLOPE

















































CONSTRUCTION



UNDERPASS PROGRESS PICTURES :


























NOTE :

-

RETAINING WALL STEP 2 AND LEAN CONCRETE OF BENCH





-

CONSTRUCT OF OPEN DRAINAGE





-

WORKING OVER NIGHT

















































CONSTRUCTION



UNDERPASS PROGRESS PICTURES :




























NOTE :

-

CONSTRUCT RETAINING WALL OTHER SIDE





-

MAKING OF SLOPE





-

CONSTRUCT OF OPEN DRAINAGE




















































CONSTRUCTION



UNDERPASS PROGRESS PICTURES :





















NOTE :









-

CONSTRUCT OF RETAINING WALL








-

CONSTRUCT OF OPEN DRAINAGE






























































CONSTRUCTION



GENERATOR HOUSE AND FUEL TANK PROGRESS 90% AND PROGRESS PICTURES AS BELOW :


CONSTRUCT OF FUEL TRAP
>

Near
Cmpletion


INSTALL OF ROOF SHEET
>
Has Completed


FINISHING
>

Still in progress
























NOTE :

-

THE REAMIN OF BUILDING ARE WALL PAINTING, FRONT DOOR AND MESH VENTILATION


-

THE REMAIN OF FUEL TRAP ARE FINISHING AND STEEL COVER PLATE

















CONSTRUCTION






CRUSHING PLANT : The currently of progress are 83.5%




The remain of the works as :


1.

Electrical : Local Control Station


2.

Main Circuit Centre


3.

Generator Set : Main Gen
-
set 415 KVA, Lighting Gen
-
set 50 KVA


4.

Install Cable : Motor to Panel, Instrument Cable


5.

Lighting : Conveyor, Lighting fixtures


6.

Civil Works : Concrete pad for Generator and also Generator house



The currently of progress as :


1.

The bolts replacement to galvanized bolts
>
Near completion


2.

Re painting of Crushing Plant
>
Near completion


3.

Digging for Generator house >
Still in progress


4.

Fabrication of rebar for the Generator house foundation
>
Near completion


5.

Back fill front of the hopper >
Not started yet and will be action by TIA Port


6.

Access Road / Entrance to Port
>
Still in progress



Note :


1.

PT BAMA need to finalization of the Organization Chart
>
Still awaiting


2.

All the drawings are not completed yet as drawings for Mechanical and Electrical also miscellaneous detail



drawings
































CONSTRUCTION





CRUSHING PLANT PROGRES PICTURES :


















NOTE :
-

NOT GOOD ENOUGH FOR THE









PROGRESS



CONSTRUCTION




Weight Bridge :
The currently of progress are 87% :



The remain of the works are :


1.

Control Room
>
Construct of building still in progress


2.

Load Cell not installed yet


3.

Installation of cable, lighting and commissioning


4.

Generator House
>
Construct of building still in progress
























































CONSTRUCTION




WEIGHT BRIDGE PROGRESS PICTURES :





























NOTE :

-

CONTROL ROOM BUILDING AND GENERATOR HOUSE
































CONSTRUCTION




BARGE LOADING CONVEYOR PROGRESS PISTURES :






























NOTE :

-

PILLING NO. SP 2.3 ; SP 2.4 ( 2 POINTS ) DONE ON NOV, 1
st

2010


-

CONSTRUCT OF TEMPORARY JETTY AND WILL BE USED FOR SUPPLY MATERIALS





























CONSTRUCTION





BARGE LOADING CONVEYOR PROGRESS PISTURES :



























NOTE :

-

PILLING NO. SP 2.5 TO SP 2.7 ( 3 POINTS ) DONE ON NOV,2
nd

2010


-

PROGRESS CONSTRUCT OF TEMPORARY JETTY


































CONSTRUCTION





BARGE LOADING CONVEYOR PROGRESS PISTURES :





























NOTE :

-

PILLING NO. SP 2.8 ( 1 POINT ) DONE ON NOV, 3
rd

2010








-

PROGRESS CONSTRUCT OF TEMPORARY JETTY


































CONSTRUCTION





BARGE LOADING CONVEYOR PROGRESS PISTURES :




























-

WORKING ON NOVEMBER, 3
rd

2010






























CONSTRUCTION





BARGE LOADING CONVEYOR PROGRESS PISTURES :

































NOTE :

-

PILLING NO. SP 2.9 ; SP 2.10 ( 2 POINTS ) DONE ON NOV, 4
th

2010






-

PROGRESS CONSTRUCT OF TEMPORARY JETTY





























CONSTRUCTION





BARGE LOADING CONVEYOR PROGRESS PISTURES :

























NOTE :

-

PILLING NO. SP 2.11 ( 1 POINT ) DONE ON NOV, 5
th

2010






-

PROGRESS CONSTRUCT OF TEMPORARY JETTY




























CONSTRUCTION





BARGE LOADING CONVEYOR PROGRESS PISTURES :






























NOTE :

-

PILLING NO. SP 2.12 ; SP 2.13 ( 2 POINTS ) DONE ON NOV, 6
th

2010






-

PROGRESS CONSTRUCT OF TEMPORARY JETTY

























CONSTRUCTION





BARGE LOADING CONVEYOR PROGRESS PISTURES :
























NOTE :

-

PILLING NO. SP 2.14 ; SP 2.15 ( 2 POINTS ) DONE ON NOV, 7
th

2010






-

PROGRESS CONSTRUCT OF TEMPORARY JETTY





























CONSTRUCTION





WORKSHOP AND OFFICE PT BAMA :



























NOTE :

-

INSTALL FORMWORK / BOUVPLANK






-

CONCRTE PAD FOR WORKSHOP AND OFFICE PT BAMA

















CONSTRUCTION





GENERATOR HOUSE FOR CRUSHING PLANT :




























NOTE :

-

CONCRETE FOUNDATION AND CONCRETE BEAM FOR GENERATOR HOUSE















CONSTRUCTION



OFFICE AND MESS ACCOMMODATION PROGRESS AS BELOW :


The currently of Office progress are :


Site preparation
>
Has completed


Underground services as Plumbing, Water Supply and Sewerage
>
Has completed


Concrete footing and concrete slab
>
Has completed





















NOTE :

-

INSTALL OF WATER SUPPLY AND SEWERAGE PIPE


-

BASE COMPACTION


-

POURING CONCRETE SLAB FOR OFFICE



















CONSTRUCTION





PORT SECURITY POS PROGRESS AS BELOW :




The currently of progress are 80 %


Construct and Install of rafter
>
Has completed


Install of the roof sheet
>
Near completion


Wall plaster
>
Near completion


Digging for septic tank
>
Still in progress








































CONSTRUCTION

Thank You