CONSTRUCTION REPORT

3 OCTOBER 2010



CONSTRUCTION

WEEKLY REPORT 27
th

SEPTEMBER


3
rd

OCTOBER 2010




PROGRESS REPORT :



CAMP HOUSING



UNDERPASS KM 204




HAULING ROAD REPAIR



PORT CRUSHING

PLAN & FACILITIES



OTHERS

:



GENERATOR HOUSE


WATER PIPE LINE



FUEL STORAGE






CONTENTS




CAMP HOUSING PROGRESS 100 % AS BELOW :



PT
Maintek

still for the repairs as per check list between PT Tunas
Inti

Abadi

and PT
Maintek

on September, 25
th

2010


The activity cover as below :
















REPAINT / RE COAT OF WALL


PRIMER / RE COAT OF WALL

REPAIR / RE COAT OF EXTERIOR WALL



















RE PAINT OF TOILET WALL


REPAIR OF CERAMIC TILE


REP
AINT / RE COAT WALL OF BED ROOM

























































CONSTRUCTION




CAMP HOUSING PICTURES :























REPAINT / RE COAT OF WALL BED ROOM


REPAIR OF THE DOOR FRAME



BED ROOM




















CLEAN UP OF CERAMIC TILE


REPAIR OF OPEN DRAIN SLOPE


REPAINT / RE COAT OF W
ALL CLADDING










































CONSTRUCTION



UNDERPASS PROGRESS AS BELOW :



The currently progress are 89.14 % :



Lean Concrete / Blinding Concrete >
Still in progress


Pouring Concrete Rigid >
Still in progress, will be finished on October, 4
th

2010


Making sloping of retaining wall in both side >
Still in progress


The open of coal hauling at the Underpass, using of one way ( right way from of the Mine ) >
Open on Oct, 1
st

2010






















POURING OF RIGID PAVEMENT


POURING OF RIGID PAVEMENT CONCRETE


NIGHT SHIFT
OF POURING CONCRETE































CONSTRUCTION



UNDERPASS PROGRESS PICTURES :














PREPARE OF COAL HAULING ROAD


SPREADING BASE COARSE AND COMPACTING FILL IN THE ASPHALT IN

THE JOINT CONCRETE





















PREPARE OF COAL HAULING ROAD PREPARE OF COAL HAULING ROAD



RAINY / WET
CONDITION



























































CONSTRUCTION



UNDERPASS PROGRESS PICTURES :












TRIAL COAL HAULING AT THE UNDERPASS


TRIAL COAL HAULING DIRECT TO PIT

TRIAL COAL HAULING FROM PORT





















TRIAL COAL HAULING EMPTY TRUCK


TRIAL COAL HAULING EMPTY TRUCK



TRIAL COAL HAULING FROM PORT





























































CONSTRUCTION




HAULING REPAIR AT THE PALM ROAD :



Held of Meeting between PT Tunas
Inti

Abadi
, PT
Ciipta

Kridatama
, PT
Malindo

on September, 30
th

2010


Present : PT TIA : Beverly Shutt, Dwi Setyo Nugroho, Budi Patria, Sukram, C. Adi
Tamtomo
, Nurcahyo,
Indra

Baudewa
.



PT CK :
Gandi

Poerwadi
,
Heri

Suparjo
,
Kristanto
, Douglas also PT
Malindo
.



Agenda of meeting :


Hauling Road Repair


Mine Plan : 3 million ton of coal plan on 2011, Creek divert.



The Priority of the jobs are Hauling Road Repair at Empty Trucks Road :



Need of units equipment :

1.
Excavator PC 320 provided by PT CK

2.
Dozer D 7 provided by PT
Malindo

3.
Compact smooth drum provided by PT CK

4.
DT provided by PT
Malindo

: 4 units

5.
Lowboy provided by PT
Malindo

to used of Excavator
mobilIzation

from Pit to KM 20



Check on site September, 30
th

2010 after meeting.


Mud Removal : dumping at the edge of hauling road near of the fishpond.


Hauling of good material from Pit to the Empty road.


Prepare of Culvert /
gorong



gorong
.


Prepare of Base Coarse from
Batu

Licin
.


Do these jobs are : road increase level at the 3 point, replace culvert more the bigger, making good drain
both side, making sump or box control at upstream and downstream.






































































CONSTRUCTION







































































CONSTRUCTION

Job Plan

September to October 2010

30

1

2

3

4

5

6

Moving Equipment



























Mud Removal



















Good Material from the Pit













Base Coarse













































































September, 30 '2010 : 14:00 wita check to location

October, 1 '2010 : Mud Removal and Dumping Good material from the Pit

October, 2 '2010 : Mud Removal and Making of drainage both side






HAULING ROAD CHECK PICTURES :















JUCTION HAULING ROAD


HAULING ROAD REPAIR STEP 2


HAULING ROAD

REPAIR STEP 3





















HAULING ROAD REPAIR STEP 4


HAULING ROAD REPAIR STEP 5


HAULING ROAD
REPAIR STEP 6














































CONSTRUCTION






HAULING ROAD CHECK PICTURES :
















HAULING ROAD REPAIR STEP 7


HAULING ROAD REPAIR STEP 8


HAULING ROAD REPAIR S
TEP 9





















HAULING ROAD REPAIR STEP 10















































CONSTRUCTION






HAULING ROAD PROGRESS PICTURES :
















MUD REMOVAL



MUD REMOVAL



COLLECT OF MUD





















GOOD MATERIAL DUMPING SPREADING BY DOZER 7


HEAV
Y RAIN AROUND 45 MINUTES










































CONSTRUCTION






HAULING ROAD PROGRESS PICTURES :
















COLLECT OF MUD STEP 2


COLLECT OF MUD STEP 2



COLLECT OF MUD STEP 2





















COLLECT OF MUD STEP 2



COLLECT OF MUD STEP 2


































CONSTRUCTION




Crushing Plant :
The currently progress are 83 %




The remain of the works are :


1
.


Electrical : Local Control Station.


2.


Main Circuit Centre.


3.


Generator Set : Main
Genset

415
Kva
, Lighting
Genset

50
Kva
.


4.


Install Cable : Motor to Panel, Instrument Cable.


5.


Lighting : Conveyor, Lighting fixtures.


6.


Civil Works : Concrete 35
Mpa

(reinforcement steel and pilling)


7.


Installation and Commissioning.



The currently progress are :


1.

Concrete Retaining Wall step 5 >
Has completed, remove of formwork also has completed


2.

Replace the bolts to galvanized bolts >
Near completion


3.

Mobilization and unloading pipe piles >
In progress


4.

Fabrication reinforcing steel and pouring concrete beam in the concrete wall


5.

The Progress is very slow


6.

Prepare of Control room pad >
Not finished yet



Note :


Need to meet and discuss about the Layout and Final Design with PT
Bangun

Arta

Hutama

:


1.

PT BAMA has sent to PT TIA of Organization Chart


2.

All the drawings has sent to PT TIA but still need to meet and discuss


















CONSTRUCTION




Progress Pictures :











THE AREA ARE WET CONDITION


THE ACCESS ROAD ARE WET CONDITION

THE SAME PROBLEM




















ACCESS ROAD TO PORT




ACCESS ROAD TO PORT


















CONSTRUCTION




Progress Pictures :












ACCESS ROAD TO PORT


ACCESS ROAD TO PORT



CONCRETE WALL AND HOPPER











CONCRETE WALL BEAM





CONCRETE WALL BEAM



REINFORCING STEEL


















CONSTRUCTION




Weight Bridge :
The currently progress are 70.5%




The remain of the works are :



1.


Control room.


2.


Load Cell.


3.


Installation Cable, lighting and Commissioning.


4.


Prepare of control room pad.



Remarks : There is no activity, still awaiting about the control room. Any two choice of construct building :
container or the brick wall → need to discuss







































CONSTRUCTION




Stock Pile Area :
The currently not filled yet





No progress

















CONSTRUCTION





Port Camp and Office : No Activities until Now



PT
Maintek

not starting yet, needed to add of the materials filling wide and long of area for buildings.


The currently no progress

















NO PROGRESS




CLEARING AREA TOO FAR

















CONSTRUCTION




OTHERS :


MINE OFFICE AREA AT THE PARKING AREA












NEED GRAVEL OR PAVING BLOCK


NEED CONSTRUCT OF OPEN DRAIN


NEED GRAVEL NEAR OF CLINIC










NOTE :
















Need to Attention for this area.












NEED CONSTRUCT OF OPEN DRAIN


NEED GRAVEL OR PAVING BLOCK


















CONSTRUCTION




OTHERS :



GENERATOR HOUSE PROGRESS 22,9 % AND PICTURES ARE BELOW :


Install
Batako

wall >
In progress


Construct of Oil trap >
Still in progress



















INSTALL BATAKO WALL




INSTALL BATAKO WALL









































CONSTRUCTION




GENERATOR HOUSE PROGRESS PICTURES :













CONSTRUCT OF OIL TRAP


CONSTRUCT OF OIL TRAP



















WALL
















CONSTRUCTION




COMMUNICATION AREA :
Need to attention for this area.


1.
Radio Communication Tower

2.
IT Tower

3.
Television Parabola Disc














NEED SOME GRAVEL AND FENCING


NEED SOME GRAVEL AND FENCING


NEED GRAVEL AND FENCING AROUND THIS AR
EA
























CONSTRUCTION




DIGGING OF THE WATER PIPE LINE :
Progress are 52 %


By CV
Tirta

Anugerah

Lestari













DIGGING PROGRESS



WATER PIPE LINE INSTALL


WATER PIPE

LINE INSTALL




















WATER PIPE LINE INSTALL


PIPE LINE BACKFILL


PIPE LINE CROS
S OF DRAINAGE





























CONSTRUCTION




FUEL STORAGE PROGRESS AS BELOW :


Construct foundation of building














FUEL STORAGE FOUNDATION





FUEL STORAGE FOUNDATION


















FUEL STORAGE FOUNDATION





FUEL STORAGE FOUNDATION

































CONSTRUCTION

Thank You