Port

jumpclaybrainedUrban and Civil

Nov 25, 2013 (3 years and 6 months ago)

127 views

Monthly

Report


PT Tunas

Inti Abadi


Monthly Report

Page
1

of
4










PT TUNAS INTI ABADI




Banjarmasin Office :

Site Communication:


Jl. Pramuka No 10 RT 18 Sebamban,
Kec. Sungai Loban

Banjarmasin 70249 Kalimantan Selatan Kabupaten Tanah Bumbu, Kalimantan Selatan

Phone : 0511
-
327 2895 ; 325 9687 Phone : 021
-
7918 2244 ; 79
18 2444

Fax : 0511
-

325 9587 Fax : 021
-
7918 2579




DATE

June,
7
st


2010

TIME

10.00 am

VENUE


PROJECT

Camp Accommod
ation, Mine Office,

Others



SUBJECT

Monthly Report on May

2010

FROM

C. Adi Tamtomo

(CAT)



COPIES

Pak

Setyo Feri
y
anto

(SF)


Ibu Indriyati Yovita
(IY)

Pak

Eddy Nugroho
(EN)



Pak Hari Sutikno
(HS)

Pak

Heru Cahyono

(HC
)


Pak
Budi Patria
(BP)




Pak


Fazrin Nor
(F
N)

Pak Arifin (ARF)




Pak Dwi Setyo Nugroho

(DSN
)

Ibu Erna (ERN)




Pak

Ichwan Satya Taqwa
(IST)






DESCRIPTION

Action by
Whom

Action by When

/ Done

1.

Mine Office



1.1


1.2

1.3

Order Partition
by an e
-
mail on June, 2
nd


2010
for
capacity of
the two rooms behind of the S
urveyor room.

Awaiting for Approval.


Install and erection of the new tower for IT back of the Mine Office. Start of work on June, 1
st

2010

Landscaping around of the Mine Office.
Still awaiting for Approval


ARF/ES

CAT/IST

CAT/HS



Monthly

Report


PT Tunas

Inti Abadi


Monthly Report

Page
2

of
4


DESCRIPTION

Action by
Whom

Action by When

/ Done

2.

Camp Accommodation

/ Site Area



2.1


2.2

2.3

2.4

2.
5

2.6

2.7

2.8

Land clearing area for the prepare of the Camp Accommodation for the 24 persons.
Will
going to

do by
PT Maintek also needed of the base course approx 400 m³ for the filling area.

Construct of the Water Treatment Plant.
The Location has

to

cleared and WTP will going to do by PT
CV Tirta Anugrah Lestari started of work on June, 3
rd

2010.

Nursery,

the Location has to cleared
.
This job will going to do by
CV Pangestu, the river stone has to
arrive on site.

Pantry for the Manager House, still in proceed in PT TIA HO including some accessories.

Need to attention for the several buildings i.e : Laundry
, Logistic, Generator House ( still awaiting for
approval),
Small Wash Pad, Fuel Storage, Power Line by PT PLN (still awaiting for approval)

Canteen need to fill of some equipment like as : table for the dining room, cooking table etc.

Water Pipe Line all
of the Accommodation area will be to designed and proposed immediately.

Renovation of the old buildings: bath room floor, electrical, water pipe line painting for the next plan

CAT/IST


CAT/IST/HS


CAT/IST/HS

ERN/ARF

HC

ERN/ARF

CAT/IST

CAT/IST







Monthly

Report


PT Tunas

Inti Abadi


Monthly Report

Page
3

of
4


DESCRIPTION

Action by
Whom

Action by When

/ Done

3.

3.1


3.2

3.3

3.4


Underpass KM 204.3 :

The Currently progress
in
attain unto approximately

57,20
%

of
the
site physical.


The steel Girder
has completed to erection, install of the form work and fabrication of reinforcing
steel
.


Pouring Concrete with 25 MPa
at the wing wall both side western of the Underpass. Install form
work both side of concrete wing wall eastern of the Underpass.


Back fill between of the concrete wing wall
both side.



CAT




4.

4.1

4.2

4.3


4.4


4.5


Port :

Prepare of the area fo
r Crusher Port.
Concret
e pad for Crusher has completed, pouring
concrete on
May, 16
th

2010
, pouring concrete for stacker pad near completed.


Port Camp and Office.
Filling area

still in progress.


Concrete foundation for Weight Bridge.
Has completed
,
pouring concrete on May, 14
th

2010
, erection
of the steel beam has completed. The currently still awaiting for the load cell.


Erection of the Crusher Plant, Conveyor, and Stacker still in going.


Prepare of the Settling Pond area.


CAT




Monthly

Report


PT Tunas

Inti Abadi


Monthly Report

Page
4

of
4


DESCRIPTION

Action by
Whom

Action by When

/ Done

5.

5.1


5.2


5.3



5.4



5.5


5.6

Others :

Generator Set.
Has arrive to site but still awaiting for Generator house budget approval.


Install temporary cable power from old Generator to Manager House and Canteen.
Has Completed.


Nursery, Water Treatment Plan.
Contract
progress and still awaiting units like Dozer and Excavator
to prepare for the location.



Three option of the design layout Camp Accommodation.
The choice option are number 3 ( one
building)


Install Power Cable for the all site.
Still awaiting for Approva
l.


Water Treatment Plan
t
.
The Quote already approved and still
in
contract progress.





Done





Done