CONSTRUCTION WEEKLY REPORT

foulgirlsUrban and Civil

Nov 15, 2013 (3 years and 6 months ago)

88 views



CONSTRUCTION WEEKLY REPORT


APRIL 2011



CONSTRUCTION

WEEKLY REPORT 25
th

APRIL


1
st

MAY 2011




PROGRESS REPORT
:





LAYOUT UNDERPASS
FACILITIES :



CONSTRUCT OF SECURITY POS BUILDING










PORT AND OTHERS
:



CRUSHING PLANT AND
BACKFILLING


BARGE LOADING CONVEYOR


OFFICE AND MESS BY PT MAINTEK







CONTENTS



LAYOUT DRAWING PLAN OF THE UNDERPASS FACILITIES AS BELOW :













































































































CONSTRUCTION




SECURITY POS OF PROGRESS PICTURES :






























NOTE :

-

POURING CONCRETE OF FOOTING


-

FABRICATION OF REINFORCING STEEL FOR TIE BEAM

































































































CONSTRUCTION




SECURITY POS OF PROGRESS PICTURES
:




















QQQQQQQ


NOTE :

-

POURING CONCRETE BEAM






-

POURING CONCRETE SLAB












































































































CONSTRUCTION





CRUSHING PLANT :
The currently of progress are 99.58%




The currently of progress as :


1.

The bolts replacement to galvanized bolts
>
Near
completion.


2.

Re painting of Crushing Plant
>
Near
completion.


3.

Back filling in front of the Hopper >
Has completed.


4.

Wiring power cable including cable tray in the Crusher >
Still in
progress.


5. Back
filling of
stock
pile >
Has completed.


6.

Electrical Check List for Crushing Plant >
Repair and
additional.




The remain of jobs as :


1.

Re painting of steel hopper and others steel frame >
Near
completion.


2.

Commissioning Crushing Plant >
Not final
yet and a waiting repair refer to check list.


3.

Concrete slab apron of Hopper >
No need of concrete but will be changed with stone mountain and top



coarse.



Note :


1.
Electrical
drawings

>
Not
completed
yet.


2. Time frame >

Prepared by every week.


3. No progress construction, the remaining of modification screen hopper and step ladder.


4. Coal stock and Crushing >
Continue.




































CONSTRUCTION




HOPPER CRUSHING PLANT MODIFICATION :

































NOTE :

-

MODIFICATION OF STEP LADDER AT THE HOPPER


-

MODIFICATION OF HAND RAILING


-

MODIFICATION OF STEEL SCREEN
















CONSTRUCTION




HOPPER CRUSHING PLANT MODIFICATION :

































NOTE :

-

MODIFICATION OF STEEL SCREEN AT THE HOPPER


-

FABRICATION OF STEEL STOPPER














CONSTRUCTION




BARGE LOADING CONVEYOR :
The currently of progress are
28.927% :




Progress of Barge Loading Conveyor are :


Fabrication and Install of reinforcing steel / rebar from SP 2.2 to SP 2.9; SP 3.1 to SP 3.6; End Tower 1 ;
2; Reclaim and BLC Hopper and also TT3 ( offshore )


Cutting pipe pile of dolphin ( offshore )


Plan to Erection of structure / truss at the SP 1; SP 2; TT1; TT2, these jobs waiting for crane unit.


Reclaim : concrete slab has completed, preparation of concrete wall and fabrication of reinforcing steel /
rebar.


BLC Hopper : dewatering / pump out of water and preparation of concrete.























CONSTRUCTION




BARGE LOADING CONVEYOR
OF PROGRESS PICTURES :





































NOTE :
-

ERECTION OF STEEL BEAM AT TT2




-

FABRICATION / INSTALL OF FORMWORK AT TT3




-

FABRICATION / INSTALL OF REINFORCING STEEL AND FORMWORK AT SUPPORT PEDESTAL











CONSTRUCTION




BARGE LOADING CONVEYOR
OF PROGRESS PICTURES :





































NOTE :

-

RIVER SAND FILL IN THE PIPE PILE


-

FABRICATION OF REINFORCING STEEL / REBAR


-

FABRICATION / INSTALL OF FORMWORK


CONSTRUCTION



PORT OFFICE AND MESS ACCOMMODATION OF PROGRESS PICTURES
:























NOTE :

-

INSTALL INTERNAL WALL, EXTERNAL WALL, INSTALL CERAMIC TILE AT THE CANTEEN BUILDING


-

CONSTRUCT OF OPEN DRAIN AROUND THE BUILDING



































































CONSTRUCTION






PORT
OFFICE AND MESS ACCOMMODATION OF PROGRESS PICTURES
:























NOTE :

-

INSTALL OF TELECOMMUNICATION


-

EXTERIOR CEILING PAINT


-

CONSTRUCT OF OPEN DRAIN AROUND THE BUILDING


-

UNDERCOAT OF WALL
















































































CONSTRUCTION



PORT OFFICE AND MESS ACCOMMODATION OF PROGRESS PICTURES
:






















NOTE :

-

WIRING ELECTRICAL CABLE FOR CEILING LAMP


-

INSTALL OF CEILING FRAME AT MESS CAMP


-

INSTALL CERAMIC FLOOR AT THE TOILET












































































CONSTRUCTION



PORT OFFICE AND MESS ACCOMMODATION OF PROGRESS PICTURES
:






















NOTE :

-

WIRING ELECTRICAL CABLE POWER


-

EXTERNAL CEILING FRAME












































































CONSTRUCTION



PORT OFFICE AND MESS ACCOMMODATION OF PROGRESS PICTURES
:























NOTE :

-

INSTALL WALL INSULATION OF CAMP BUILDING


-

PREPARATION OF WALL PAINTING


-

PAINTING OF CEILING


-

PAINT OF FUEL TANK, INSTALL FUEL LINE, AND MUFFLER