SENIOR PROJECT PROGRESS REPORT

beaverswimmingAI and Robotics

Nov 14, 2013 (3 years and 11 months ago)

96 views

SENIOR PROJECT PROGRESS REPORT


Name:



Chris Spikes

Date:


4/17/01
-
4/24/01

Project title:

Automatic Adhesive Application

Sponsor:

ASC


My accomplishments since last report:



Meet with ASC and obtained capital approval for our bill of material components.



R
ectified the situation with the pail unloader. We will able to use the pail unloader at least twice
this summer.



Meet with Dr Jack to discuss our motion control and possible options and pitfalls.



I updated the Gantt chart to reflect progress on the report
.


Major problems to date:



Upon meeting with Dr. Jack, or motion control system must be researched more in depth before
ordering. This may set us back a week in that area of the project.


Objectives:



Coordinate with ASC’s purchasing department, Mike Yost,

and engineering to allow for prompt
ordering of components.