Penn State University


All Rights Reserved

The Pennsylvania State University

Abington College

Information Sciences and Technology

IST 302


Information Technology Project Management

Fall 2013

Assignment 6


Initial Project Plan with Resource Assignment
















Background


In Assignment 4
and Assignment 4b, a Work Breakdown Structure (WBS) was developed. That WBS was
used in Assignment 5 to prepare the initial cost plan and draft task network with modifications to the
WBS made as necessary.


Students will use the initial cost plan and draf
t task network prepared in Assignment 5 as inputs to be
modified with the assignment of specific personnel resources.


Problem Scenario:


The Yons Corporation has decided to implement a new electronic (i.e., computer
-
based) project
management application s
ystem (name PROM). After conducting the necessary due diligence, the
company has identified and selected a COTS (commercial off the shelf) software tool. The product has
been acquired and a project to install and deploy it has been initiated. The projec
t (name YPM) has now
entered the planning stage.


The project management tool (PROM) that was selected features thin
-
client architecture and is built upon
an IBM DB2
®

database. Yons’ environment features Microsoft Windows
©
-
based clients, an IBM
mainframe
server with the AIX
®

operating system, and the most recent version of DB2
®
. Project
management histories from previous project exist in both electronic and non
-
electronic formats.


The YPM project will involve the following: (i) installation and checkout

of PROM; (ii) data conversion of
electronic project history data; (iii) determination and disposition of non
-
electronic project history data;
(iv) user documentation and training; (v) user acceptance testing; and, (vi) deployment.


General parameters are
provided:



Labor

o

Project Manager
-

$40.00/hour

o

System Analysts



Senior
-

$35.00/hour



Associate
-

$28.00/hour



Junior
-

$22.00/hour

o

Data Analysts
-

$30.00/hour

o

Programmers



Senior
-

$32.00/hour



Associate
-

$27.00/hour



Junior
-

$20.00/hour

o

Trainers
-

$24.00/hour

o

Users
-

$28.00/hour

o

Testers
-

$29.00/hour



Benefits


25%



G & A


12%

IST 302



Information Technology Project Management

Fall 2013

Assignment 6


Initial Project Plan with Resource Assignment

© Ed Green

October 31, 2013

2


Penn State University


All Rights Reserved


The project is to start no later than November 1
st

2013 and must be completed no later than the end of the
first calendar quarter of 2014.


Specific personnel ava
ilability for the
YPM

project is as follows:


Position

Person

Rate

(1)

Notes

(2)

Project Manager

Joe Apple

$37.00

Will spend 50% of time applied to
YPM

Senior Systems Analyst

Maria Smith

$34.00

Available 100% of time for
YPM

Senior Systems Analyst

Ashley Baker

$36.00

Available 15% of time for
YPM

Associate Systems Analyst

Bella Sony

$28.00

Available 100% of time for
YPM

Associate Systems Analyst

Sammy Hammer

$24.00

Available 100% of time for
YPM

Associate Systems Analyst

Mary Brown

$29.00

Available 30% of time for
YPM

Junior Systems Analyst

Jeffrey Jones

$22.00

Available 100% of time for
YPM

Junior Systems Analyst

Warren Tower

$22.00

Available 100% of time for
YPM

Data Analyst

Thomas Plumb

$30.00

Available 50
%

of time for
YPM

Data
Analyst

Ashley Black

$30.00

Available 50% of time for
YPM

Senior Programmer

Casey Jackson

$30.00

Available 30% of time for
YPM

Associate Programmer

James Wilson

$25.00

Available 30% of time for
YPM

Junior Programmer

Karen Plumb

$20.00

Available 30% of t
ime for
YPM

Trainer

Jackie Trainer

$24.00

Available 50% of time for
YPM

User

Jack Right

$42.00

Available 20% of time for
YPM

User

Mark Progress

$43.00

Available 20% of time for
YPM

User

Helen Even

$42.00

Available 20% of time for
YPM

Tester

Zack
Markers

$29.00

Available 100% of time for
YPM

Tester

Davis Captain

$29.00

Available 50% of time for
YPM

Tester

Frank Carpel

$30.00

Available 25% of time for
YPM


(1)

Hourly rate exclusive of benefits and G & A.

(2)

Indicates the
maximum

amount of time that the
individual is available for project work during a
given work week.

Table 1


Personnel available for assignment to
YPM

project with labor rates.


In reviewing the project management materials submitted for review, it was noted that no provision for
managem
ent activities was included. It was directed that a fixed amount of time (called a
level of effort

task) be
added

to the project plan. This management task is to be performed by the project manager and
will begin on the day the project begins and continu
e until the project concludes.


Deliverables:


There are three deliverables for this assignment.


1.

An initial cost plan presented in the format used in slide 21 of the
Project Planning

slide deck

2.

A draft task network following the model presented in slide 27 of the
Project Planning
slide deck.

3.

A comprehensive set of lessons learned for both individuals and the team.


In addition, changes made to the WBS from Assignment 4b in the conduct of this ass
ignment should be
submitted as well.


Assignment



This assignment requires the preparation of the cost plan and task network that will be presented for
management approval and used to begin the execution of the YPM project. Each instructor
-
assigned
© Ed Green

October 31, 2013

3


Penn State University


All Rights Reserved

team will operate
as the project planners to produce a viable set of deliverables suitable for management
review and approval as well as being necessary and sufficient to manage program start up


As noted above, this assignment will be performed by the ins
tructor
-
assigned IST 302 teams. Only those
individuals who fully participate in their team’s work efforts are eligible to receive credit for this
assignment.


Preparation Directions:


The initial cost plan is to be presented in the format noted above. To

facilitate the preparation of this
deliverable, the use of spreadsheet technology (Microsoft Excel
©

or equivalent) shall be used. To facilitate
the preparation of the task network in the format required, drawing technology (Microsoft PowerPoint
©
,
Microso
ft Visio
©
, or equivalent) shall be used. Changes to the WBS shall be indicated in a copy of the
Assignment 4b WBS document using the Microsoft Word
©

Track Changes

facility.


Work products for this assignment shall be submitted
electronically
. The
structure of the submission
shall be a Microsoft Windows
©

folder named
Team_x_Assignment_6

where
x

is the team number. The
contents of the folder shall be as follows:


1.

A document file named
Members.docx

which contains the names of the team members who
par
ticipated in completing the assignment.

2.

A spreadsheet file named
CostEstimate.xlsx

which contains the initial cost estimate for the
project.

3.

A drawing file named
TaskNetwork.pptx

which contains the initial task network for the project.

4.

A document file named
WBS.docx

which contains the modifications to the work breakdown
structure.

5.

A document file named
LessonsLearned.docx

which contains the comprehensive set of lessons
learned.


Electronic deliverables shall be prepared so as to be easi
ly readable. Fonts such as Ariel, Verdana, and
Tahoma are recommended.


Work products shall be submitted by transferring student materials to an instructor
-
provided flash drive
on the day the assignment is due. The transfer shall involve the movement o
f the team’s folder only.


This assignment is due on Thursday, October 24
th

2013

.