Business Integration Update to PRS
June 2011
Includes:
•
2011 Project Portfolio Update
•
Parking Deck Impact Assessment
•
2012 Project Prioritization
2
–
2011 Project Portfolio Update
p. 3
-
7
•
Project Portfolio Gantt Chart
–
Sorted by go
-
live date
•
Recent Developments
–
Parking Deck Impact Assessment
p. 8
-
10
•
Introductory Comments
•
Impact Assessment Results
•
Endorsement Consideration (vote)
–
2012 Project Prioritization
p. 11
-
20
•
Schedule
•
Introductory Comments
•
Funding
Summary
•
Details by Project Category
•
Endorsement Consideration (vote)
–
Appendix
p.
21
-
26
•
Summary Project Descriptions
Business Integration Update
–
Agenda (revised)
3
Date
Project Portfolio
–
as of 6/13/2011
–
Sorted by Go
-
Live Date
4
Date
Project Portfolio
–
as of 6/13/2011
–
Sorted by Go
-
Live Date
5
Date
Project Portfolio
–
as of 6/13/2011
–
Sorted by Go
-
Live Date
6
Date
Project Portfolio
–
as of 6/13/2011
–
Sorted by Go
-
Live Date
7
Project Portfolio
–
Recent Developments
•
TAC and Board Approved Several Additions to the PPL
–
NPRR310, NPRR350, SCR764
•
Go
-
Lives Planned for June / July
–
NPRR285
–
Settlements portion
•
Effective 6/6/2011
–
NPRR341
–
Remove AS Offers from SASM that Do Not Meet the Lead Time
•
Effective 6/22/2011
–
NPRR339
–
Modifications to Heuristic Rules
•
Effective 6/22/2011
–
Day Ahead and Real Time
•
Effective 7/20/2011
–
CRR
–
NPRR146
–
ICCP Telemetry Information Submittals
•
Effective 7/1/2011 if Board approves at June meeting
–
NPRR323
–
Correct DAM Credit Exposure Language and Enable Qualified Expiring
CRRs to Offset PTP Bid Exposure
•
Effective 7/20/2011
–
NPRR282
–
Dynamic Ramp Rates Use in SCED
•
Effective 7/22/2011
8
Parking Deck Impact Assessments
–
Phase 2 / 3
–
Comments
•
ERCOT has completed the Impact Analysis for 10 of the NPRRs in the
Phase 2 / Phase 3 portion of the Parking Deck
–
Summary of results on the next slide
•
Since the 2012 project prioritization process is also underway, ERCOT has
suggested delivery targets for these NPRRs
–
See “Delivery Target” column on the next slide
–
These dates coincide with future year funding recommendations
(slides 16
-
17)
•
CBAs
–
CBAs for these Parking Deck items are being worked in parallel with the approval
process
–
Goal: Have draft CBAs ready for 6/23 PRS meeting and final CBAs ready for 7/7 TAC
•
ERCOT will initiate market discussions on the remaining Parking Deck
items
–
These items will benefit from additional discussion before the IAs are completed
9
Parking Deck Impact Assessments
–
Phase 2 / 3
–
IA Results
Rev
Request
Description
Estimated
Cost
Estimated
Duration
Delivery
Target
NPRR181
FIP Definition Revision
$210k
-
$225k
10
-
12 weeks
2013
NPRR207
Unit
Deselection
$50k
-
$55k
9
-
11 weeks
2012
NPRR210
Wind Forecasting Change to P50, Sync w/PRR841
$45k
-
$55k
8
-
16 weeks
2013
NPRR222
Half
-
Hour Start RUC
Clawback
$15k
-
$20k
5
-
7 weeks
2012
NPRR240
Proxy Energy Offer Curve
$50k
-
$60k
12
-
14 weeks
2013
NPRR241
AIL
Calc
and Credit Reports Publish Corrections
$100k
-
$120k
5
-
10 months
2013
NPRR244
Clarification of Other Binding Documents
$10k
-
$15k
n/a
2011
NPRR256
Sync w/PRR787, Add Non
-
Compliance Language to QSE
Performance Standards
$120k
-
$135k
9
-
10 months
2013
NPRR258
Sync with PRR824 and PRR833
$55k
-
$60k
8
-
10 weeks
2011
NPRR272
Definition and Participation of Quick Start Generation Resources
$145k
-
$160k
20
-
22 weeks
2012
NPRR257
Synchronization with Nodal Operating Guide Section 9,
Monitoring Programs
TBD
TBD
TBD
NPRR260
Providing Access to MIS Secure Area to MIS Registered Users
TBD
TBD
2012
NOGRR034
Rescind Telemetry Performance Calculation Exclusions
TBD
TBD
TBD
SCR755
ERCOT.com Website Enhancements
TBD
TBD
TBD
Further Discussion with the Market Requested
Completed Impact Analyses
*
*
O&M effort
–
no project required
10
–
Suggested endorsement language:
•
PRS endorses the Impact Analysis documents for the following Parking
Deck revision requests :
–
NPRR181: FIP Definition Revision
–
NPRR207: Unit Deselection
–
NPRR210: Wind Forecasting Change to P50, Sync with PRR841
–
NPRR222: Half
-
Hour Start RUC Clawback
–
NPRR240: Proxy Energy Offer Curve
–
NPRR241: Aggregate Incremental Liability (AIL) Calculation and Credit
Reports Publish Corrections
–
NPRR244: Clarification of Other Binding Documents
–
NPRR256: Sync with PRR787, Add Non
-
Compliance Language to QSE
Performance Standards
–
NPRR258: Sync with PRR824 and PRR833
–
NPRR272: Definition and Participation of Quick Start
Generation Resources
Parking Deck Impact Assessments
–
Phase 2 / 3
–
Endorsement
11
2012 Project Prioritization
–
Schedule
•
April 2011
–
ERCOT prepares draft 2012 project list and reviews schedule with market
•
Request input from the market on new additions
•
May 2011
–
Initial review at market subcommittee meetings
•
COPS
(May 10)
•
WMS
(May 11)
•
ROS
(May 12)
•
RMS
(May 18)
•
June 2011
–
Approval/endorsement by market subcommittees
•
COPS
(June 14)
•
WMS
(June 15)
•
ROS
(June 16)
•
RMS
(June 22)
•
PRS
(June 23)
•
July 2011
–
Approval/endorsement by TAC
(July 7)
–
Available for F&A and Board review
(July 18)
COPS endorsed 3 changes in rank
12
2012 Project Prioritization
–
Introductory Comments
•
ERCOT is working diligently to limit the 2012 budget to the most
critical needs
•
$15M has been allocated for capital projects
•
Is $15M sufficient for ERCOT’s capital project needs?
–
Answer: Yes
–
Due to the recent Data Center Hardware project, 2012 is expected to
have a more labor
-
intensive project mix than usual
–
Supporting information:
•
2012
–
total project labor estimate = 108,000 hours
•
2011
–
YTD internal PPL project labor = $2.31M (~35,500 hours)
•
2010
–
total internal PPL project labor = $2.73M (~42,000 hours)
•
2009
–
total internal PPL project labor = $3.96M (~61,000 hours)
13
Project Category Definitions
•
Key Areas of Focus (Project Categories)
–
Regulatory
•
Required by Legislature, PUCT, NERC, FERC or legal ruling
–
Business Strategy
•
Market driven enhancements and efficiencies
•
ERCOT strategic initiatives
–
Efficiencies & Enhancements
•
Internally driven operational improvements
•
Enhanced customer service
–
Technical Foundation
•
Required maintenance and upgrades
•
Technical evolution and performance
•
Systemic growth
14
2012 Project Prioritization
-
Funding Summary
Project Category
Target Funding
Projects Started in
Previous Years
New 2012
Projects
Regulatory
$ 1,600,000
2
1
Business Strategy
$ 5,950,000
5
15
Efficiencies &
Enhancements
$ 2,050,000
2
9
Technical Foundation
$ 6,500,000
4
7
Total
$ 16,100,000
13
32
ERCOT will manage within the projected $15M project funding allocation.
As active projects move through the project lifecycle and new projects are
considered for initiation, they will be reassessed for criticality, cost/benefit
and resource availability against other projects in the portfolio.
Inclusion on the preliminary 2012 PPL does not guarantee funding!
15
2012 Project Prioritization
–
Regulatory
Project Category
2012
Rank
Project
2012 Budget
2013 Budget
2014 Budget
Regulatory
1
REC Enhancements
$500k-$1M
-
-
Regulatory
2
CFTC Compliance
$100k-$250k
-
-
Regulatory
3
Compliance Software Tool
$500k-$1M
-
-
*
*
*
Projected carryover project from 2011
See Appendix for brief project descriptions
16
2012 Project Prioritization
–
Business Strategy
(page 1)
*
*
Projected carryover project from 2011
*
*
*
Project Category
2012
Rank
Project
2012 Budget
2013 Budget
2014 Budget
Business Strategy
1
TXSET4.0
$250k-$500k
-
-
Business Strategy
2
SCR760
$1M-$2M
$100k-$250k
-
Business Strategy
3
Cyber Security Project #1
$50k-$100k
-
-
Business Strategy
4
Cyber Security Project #2, Phase 1
<$50k
-
-
Business Strategy
5
TSAT Wind Model
$100k-$250k
-
-
Business Strategy
6
PRR830/NPRR269 - Reactive Power Capability
$250k-$500k
-
-
Business Strategy
7
Demand Response (Look Ahead SCED)
$500k-$1M
$3M-$5M
-
Business Strategy
8
Facilities Project
$1M-$2M
-
-
Business Strategy
9
Cyber Security Project #3
$500k-$1M
-
-
Business Strategy
10
Cyber Security Project #4
$500k-$1M
-
-
Business Strategy
11
NPRR347 - Single Daily Invoice
$50k-$100k
-
-
Business Strategy
12
NPRR260 - MIS Secure Access
$100k-$250k
-
-
Business Strategy
13
MarkeTrak Upgrade/Enhancements
$500k-$1M
-
-
Business Strategy
14
TML Transition to MIS
$100k-$250k
-
-
Business Strategy
15
Planning Site Transition to MIS
$100k-$250k
-
-
Business Strategy
16
NPRR222 - Half Hour Start Clawback
<$50k
-
-
Business Strategy
17
Cyber Security Project #2, Phase 2
$100k-$250k
-
-
*
Ranking changes by COPS
See Appendix for brief project descriptions
17
2012 Project Prioritization
–
Business Strategy
(page 2)
Project Category
2012
Rank
Project
2012 Budget
2013 Budget
2014 Budget
Business Strategy
18
NPRR326 - Adjust RT SPP Calc.
<$50k
-
-
Business Strategy
19
NPRR272 - Quick Start Resources
$100k-$250k
-
-
Business Strategy
20
NPRR207 - Unit Deselection
$50k-$100k
-
-
Business Strategy
21
Cert. Data Product Subscription Stand.
-
$100k-$250k
-
Business Strategy
22
EPS Metering DB Redesign
-
$250k-$500k
-
Business Strategy
23
NPRR181: FIP Definition Revision
-
$100k-$250k
-
Business Strategy
24
NPRR210: Wind Forecasting Change to P50, Sync with PRR841
-
<$50k
-
Business Strategy
25
NPRR241: AIL Calc & Credit Reports Publish Corrections
-
$100k-$250k
-
Business Strategy
26
NPRR256: Sync with PRR787, Add Non-Compliance Language to QSE Performance Standards
-
$100k-$250k
-
Business Strategy
27
NPRR240 - Proxy Energy Offer Curve
-
<$50k
-
Business Strategy
28
Incremental Update Capability - Phase 2
-
$1M-$2M
$1M-$2M
Business Strategy
29
MP Online Data Entry - Ph 2
-
$1M-$2M
-
Business Strategy
30
MP Online Data Entry - Ph 3
-
-
$1M-$2M
Business Strategy
31
NPRR257: Sync with NOG Section 9
-
-
-
Business Strategy
32
SCR755: Access to MIS Secure Area
-
-
-
Business Strategy
33
NOGRR034: Rescind Telemetry Perf Calc Exclusions
-
-
-
See Appendix for brief project descriptions
18
2012 Project Prioritization
–
Efficiencies and Enhancements
Project Category
2012
Rank
Project
2012 Budget
2013 Budget
2014 Budget
Efficiencies/Enhancements
1
Incremental Update Capability - Phase 1
$100k-$250k
-
-
Efficiencies/Enhancements
2
MP Online Data Entry - Ph 1
$500k-$1M
-
-
Efficiencies/Enhancements
3
CMS and MIR replacement
$250k-$500k
$500k-$1M
Efficiencies/Enhancements
4
ERCOT Website Enhancements - 2012
$250k-$500k
-
-
Efficiencies/Enhancements
5
Macomber Map NERC SA/Compliance Enhancements
$250k-$500k
-
-
Efficiencies/Enhancements
6
IGRID Implementation
<$50k
-
-
Efficiencies/Enhancements
7
Contingency Functionality Enhmts.
<$50k
-
-
Efficiencies/Enhancements
8
SMTNET Improvements
$50k-$100k
-
-
Efficiencies/Enhancements
9
MP Communications Tool
$50k-$100k
-
-
Efficiencies/Enhancements
10
Smartphone Interface ("MyGrid")
$100k-$250k
-
-
Efficiencies/Enhancements
11
OA Grid Health Operator View
<$50k
-
-
Efficiencies/Enhancements
12
Secure File Transfer
-
$50k-$100k
-
Efficiencies/Enhancements
13
EMIL and View by Protocol Enh.
-
$100k-$250k
-
Efficiencies/Enhancements
14
Replace N2N System
-
$50k-$100k
-
Efficiencies/Enhancements
15
Contract Mgmt Software
-
$100k-$250k
-
Efficiencies/Enhancements
16
Voice Analytics
-
$100k-$250k
-
Efficiencies/Enhancements
17
OTS Enhancements
-
$100k-$250k
-
Efficiencies/Enhancements
18
ERCOT Website Enhancements - 2013
-
$100k-$250k
-
Efficiencies/Enhancements
19
ERCOT Website Enhancements - 2014
-
-
$100k-$250k
*
*
Projected carryover project from 2011
*
See Appendix for brief project descriptions
19
2012 Project Prioritization
–
Technical Foundation
Project Category
2012
Rank
Project
2012 Budget
2013 Budget
2014 Budget
Technical Foundation
1
Data Center Migration
$100k-$250k
-
-
Technical Foundation
2
Minor Cap - Critical - 2012
$500k-$1M
-
-
Technical Foundation
3
Information Lifecycle Mgmt Phase 2
$500k-$1M
-
-
Technical Foundation
4
Settlement Upgrade
$1M-$2M
$1M-$2M
-
Technical Foundation
5
Oracle 11g Upgrade
$1M-$2M
-
-
Technical Foundation
6
EMS Upgrade
$1M-$2M
$3M-$5M
$1M-$2M
Technical Foundation
7
Enterprise DW Platform Transition
$500k-$1M
$3M-$5M
-
Technical Foundation
8
Job Scheduling Upgrade v8
$100k-$250k
-
-
Technical Foundation
9
Siebel Upgrade
$250k-$500k
-
-
Technical Foundation
10
NMMS Upgrade
$100k-$250k
-
-
Technical Foundation
11
DC Growth & Asset Replacement - 2012
$500k-$1M
$1M-$2M
-
Technical Foundation
12
CRR Upgrade
-
$100k-$250k
-
Technical Foundation
13
Business Intelligence Software Upgrade
-
$500k-$1M
-
Technical Foundation
14
Capacity growth - storage/comp.
-
$250k-$500k
-
Technical Foundation
15
Job Scheduling Upgrade v9
-
$250k-$500k
-
Technical Foundation
16
User Authentication Upgrade
-
$50k-$100k
-
Technical Foundation
17
Replace Sun DSEE
-
$500k-$1M
$500k-$1M
Technical Foundation
18
Replace Sun IDM
-
$500k-$1M
$500k-$1M
Technical Foundation
19
Minor Cap - Critical - 2013
-
$1M-$2M
-
Technical Foundation
20
Minor Cap - Critical - 2014
-
-
$1M-$2M
Technical Foundation
22
DC Growth & Asset Replacement - 2013
-
$1M-$2M
-
Technical Foundation
23
DC Growth & Asset Replacement - 2014
-
-
$3M-$5M
*
*
Projected carryover project from 2011
*
*
*
See Appendix for brief project descriptions
20
2012 Project Prioritization
–
Motion
Suggested Motion
Motion to approve/endorse ERCOT’s initial project rank and
preliminary funding by project category
•
<as amended by PRS>
21
Appendix
22
Project Descriptions
–
Regulatory
Rank
Project Name
Project Description
1
REC Enhancements
Enhance the REC tool to comply with PUCT rules and
incorporate additional functionality
2
CFTC Compliance
Funds for use in a project to support ERCOT’s application
for a CFTC exemption
3
Compliance Software Tool
Automate the tracking of compliance obligations
23
Project Descriptions
–
Business Strategy
Rank
Project Name
Project Description
1
TX SET 4.0
Continuation of TX SET 4.0 project
2
SCR760
SCR760 Recommended Changes Needed for Information
Model Manager and Topology Processor for Planning Models
3
Cyber Security Project #1
Enhancement to system administrator infrastructure
4
Cyber Security Project #2, Phase 1
Enhancement to virus protection
5
TSAT Wind Model
Implement wind models in TSAT application. Enhance
reliability by delivering closer to real time stability information.
6
PRR830/NPRR269
–
Reactive
Power Capability
Potential system changes needed due to final resolution
between ERCOT and market stakeholders
7
Demand Response / Look
-
Ahead
SCED
Initial planning phase of the next major evolutionary phase of
the Nodal systems (Nodal 2.0)
8
Facilities Project
Funding reserved for relocation of remaining functions from
the Met Center (if necessary)
9
Cyber Security Project #3
Enhancement to remote access capability
10
Cyber Security Project #4
Enhancement to malware protection
24
Project Descriptions
–
Business Strategy
Rank
Project Name
Project Description
11
NPRR347
–
Single Daily Invoice
NPRR347
-
Single Daily Invoice
12
NPRR260
–
MIS Secure Access
NPRR260
-
MIS Secure Access
13
MarkeTrak
Upgrade/Enhancements
Enhance underlying
MarkeTraksoftware
and deploy
enhancements agreed upon by ERCOT and market
stakeholders
14
TML Transition to MIS
Migrate remaining functions that support the Retail market
from TML to MIS
15
Planning Site Transition to MIS
Migrate Planning functions/data that currently reside on the
POI to MIS
16
NPRR222
–
Half Hour Start
Clawback
NPRR222
-
Half Hour Start
Clawback
17
Cyber Security Project #2, Phase 2
Extend capabilities developed in the phase 1
18
NPRR326
–
Adjust RT SPP Calc.
NPRR326
-
Adjut
RT SPP Calc.
19
NPRR272
–
Quick Start Resources
NPRR272
-
Quick Start Resources
20
NPRR207
–
Unit
Deselection
NPRR207
-
Unit
Deselection
25
Project Descriptions
–
Efficiencies / Enhancements
Rank
Project Name
Project Description
1
Incremental Update Capability
–
Phase 1
Provide incremental update capability to all production systems for all
model related data
2
MP Online Data Entry
–
Phase 1
Allow Market Participant and Resource registration through an electronic
user interface to submit and view MP and Resource registration
information
3
CMS and MIR Replacement
Replace applications used to deploy web content to enhance scalability
and reliability
4
ERCOT Website Enhancements 2012
Continuous improvement of www.ercot.com and public market
communications
5
Macomber
Map NERC SA/Compliance
Enhancements
Enhance the
Macomber
Map application to further address control room
situational awareness
6
IGRID Implementation
Improve operator situational awareness by bringing the Market, Outage
Scheduler and EMS into a set of operator dashboards
7
Contingency Functionality Enhancements
Enhance NMMS capabilities to allow business owners to submit, via
NOMCR, contingency group configurations with a higher level of
specificity
8
SMTNET Improvements
SMTNET time point improvements to troubleshoot time points
9
MP Communications Tool
Create a tool to be placed in market participant control rooms, to ensure
that they are receiving continual high
-
level status information
10
Smartphone Interface (“
MyGrid
”)
Create a smart
-
device (e.g., Android, Apple
iOS
, Blackberry) application
showing a high
-
level view of system status
11
OA Grid Health Operator View
Give operators a view into overall grid health that incorporates a variety
of operational parameters into a single graphical dashboard interface
26
Project Descriptions
–
Technical Foundation
Rank
Project Name
Project Description
1
Data Center Migration
Completion of Data
Center Hardware project
2
Minor Cap
–
Critical
–
2012
Critical Minor Cap items for 2012
3
Information Lifecycle Management
Phase 2
Continuation of project to implement a strategy for efficient
data storage utilization while continuing to meet Protocol data
retention requirements
4
Settlement Upgrade
Continuation of project to rewrite the modules of the
settlement system so they run more efficiently and are easier
to maintain
5
Oracle 11g Upgrade
Upgrade database software to the latest version
6
EMS Upgrade
Upgrade EMS software to the latest version
7
Enterprise Data Warehouse Platform
Transition
Evaluate the platform that is the core foundation of market
data transparency and archival requirements to determine the
long
-
term approach to increasing overall reliability and
maximize capacity utilization
8
Job Scheduling Upgrade v8
Upgrade batch job software to a more current version
9
Siebel Upgrade
Upgrade software to the latest version
10
NMMS Upgrade
Upgrade NMMS software to the latest version
11
Data Center Growth & Asset
Replacement
Funding for continued demand for growth of computing
environment (storage, servers, etc.)
Enter the password to open this PDF file:
File name:
-
File size:
-
Title:
-
Author:
-
Subject:
-
Keywords:
-
Creation Date:
-
Modification Date:
-
Creator:
-
PDF Producer:
-
PDF Version:
-
Page Count:
-
Preparing document for printing…
0%
Σχόλια 0
Συνδεθείτε για να κοινοποιήσετε σχόλιο