MIUIV BUILDING PROJECT January 2008 August 2008

bustlingdivisionΗλεκτρονική - Συσκευές

15 Νοε 2013 (πριν από 3 χρόνια και 8 μήνες)

115 εμφανίσεις

MIUIV BUILDING PROJECT


January 2008

August 2008

Cecelia H. Yauger

Executive Director

February 4, 2008

Building Staff Meeting

Approval of Project


The MIUIV Board of Directors
approved a 1.4 million dollar
Renovation Program with the
T.A.C Energy Solutions at the
December 19, 2007 meeting.


The T.A.C. Firm will begin work
on site in April 2008


Scope of Work Prior to Project


Building Modeling


Data Loggers Placed and Data
Analyzed


TAC Engineer Site Visits


Roofing Specialist Site Visits


Building Envelope Specialist Site Visit


Mid
-
Term Findings Review with Admin
and Board Members


Contractor Site Visits


Audit Finalized and Project Reviewed


Review Project


Improve Building Infrastructure


Update and Improve Building Systems


Prepare Building for Future



Improve Environmental Quality


Indoor Air Quality


Lighting Quality


Comfortable Space



Improve Energy and Operational
Efficiency


Review Project

ECM 1: HVAC System Upgrades and
Improvements


Current System Issues:



Nearing end of useful life


Contributor of poor Indoor Air Quality (IAQ)


Contributor to building comfort problems


Inefficient system combined with no ventilation



Recommended Solution:


Redesigned Variable Refrigerant Volume Heat
Pump System


Result: Improved building comfort and indoor air
quality as well as reduced energy and
maintenance costs


Review Project

ECM 2: Centralized Digital Control
System


Current System Issues:



No central control system


Contributor to high energy usage


Contributor to building comfort problems



Recommended Solution:


Install central, automatic temperature control
system integrated with new HVAC systems


Result: Improved building comfort and indoor air
quality as well as reduced energy and
maintenance costs



Review Project

ECM 3: Lighting System and Ceiling
Improvements



Current Lighting Issues:


Poor lighting layout resulting in poor lighting
quality


Outdated and inefficient lighting technology


Contributor to high energy usage


Does not conform to the current energy code




Current Ceiling Issues:


Inconsistent and difficult to maintain ceilings


Occupied spaces without dropped ceiling


Review Project

ECM 4.2: Air
-
sealing and Weather
-
stripping


Current Issues:



Building has numerous points of air
-
infiltration


Contributes to increased energy costs the
building comfort issues



Recommended Solution:


Air
-
Seal and weather strip areas such as
overhangs, soffits, roof edges, duct and pipe
penetrations, etc


Will reduce energy consumption and allow
HVAC system to operate and maintain space
temp properly


Review Project

ECM 4.1: Roofing System
Improvements


Current Issues:



Roof has leaks, primarily at the
intersection of the west additions where
there is elevation difference


Roof is out of warranty but in fair
condition


Recommended Solution:


Roof Refurbishment


Next Steps


Beginning April 14,2008 the work will
be completed in 3 phases.


Relocation of offices will occur on or
about the following 4 Target dates:



April 14, 2008



May 1, 2008



June 1, 2008



July 1, 2008


General Information


Main Entrance for visitors and
staff of the Building will be
Campbell Drive


Main Entrance for workers will be
Maple Street


Temporary Signage will be posted

Temporary Signage

Training/Meeting Relocation

April 25, 2008
-
August 31, 2008



TO: MIU Management Team Staff



Special Education Supervisors



Frew Mill Administration


FROM: Cecelia H. Yauger



RE: Facility Options



DATE: January 2, 2008



The MIU Board of Directors voted to authorize the TAC
project at the December 19, 2008 board meeting.


As discussed at the staff meetings in October, November,
and December, the project will temporarily prohibit the
use of the training and conference rooms in the MIUIU
main office beginning on
April 25, 2008.


Most, if not all activities scheduled to be hosted at the
MIU IV will need to be relocated.


May 2008 Relocation

Needs/Plans


April 28
-

Network Mtg
-

SB


Tac Mtg
-

SB

April 29
-

Sail Mtg
-

SB

April 30
-

PIL
-
KZ


Parent Toolbox
-

FC

May 1
-

PIL

KZ


LTF
-

FC

May 5
-

Sped Staff
-

FC


Non Public
-

EN

May 7
-

SAC
-

CY

May 8
-

MATH 3
-

SB


LTF
-

FC

May 12
-

PSERS
-

JS

May 13
-

Math Core
-

SB


Sail Core
-

SB

May 14
-

Emotional Support
-

SB


Interviews


HR

May 15
-

Pupil Transpiration Cord.


JS

May 16
-

Sped Contact Meeting


FC

May 19
-

Network/TAC Mtg
-

SB

May 20


PA Trust Meeting

BB


Sped Planning


FC


Arts/Humanities
-

VM

May 21
-

Staff, L/M,


Board
-

CY
---

GROVE CITY SCHOOL DISTRICT BOARD ROOM

May 22
-

School Wide Behavior Support
-

SB


OT/PT Staff
-

JK



June 2008 Relocation
Needs/Plans


June 5
-

LICC
-

AL


EI Core
-

AL

June 10
-

PSERS
-

JS

June 11
-

Emotional Support
-

SB

June 17
-

PANA
-

JM

June 18
-

PIL

KZ

June 19
-

PIL

KZ

June 24
-

PIL
-

KZ


Arts/Humanities
-

VM

June 25
-

PIL
-

KZ

June 26
-

Staff/Board
-

CY



July 2008 Relocation
Needs/Plans

No meetings scheduled at this
time.


August 2008 Relocation
Needs/Plans


August 13
-

Staff/Board
-

CY



August 19
-


Best Practices/GCHS

August 20
-
23 Sped In
-
service
-
FC

Group 1 Relocation

April 14, 2008



Charles Dumbaugh
-
IMS


Brian Grossman
-
IMS


Rick Magargee
-
IMS


Josh Thompson
-

IMS

Group 1 Relocation

May 1, 2008


Olivia Allison
-
Exterovich

CCIS


Teresa Beatty

CCIS


Jim Bennett Conference Room A/B


Susan Black
LGI 2


PJ Burchfield

CCIS


Terri Clark
LGI 2


Sally Conley Lobby of LGI


Judy Dennis
LGI 2


Fingerprint Station Alcove of LGI


Veronica Gardner
LGI 1


Robert Ghering Conference Room A/B


Beth Glew
Franklin


Dave Hofing Conference Room A/B


Linda Howard
147



Cheryl Karns
LGI 1


Marilyn Kay
LGI 1


John Kassi
LGI 2


Jacque Kendall
172


Maggie Kishbaugh
LGI 1


Susie Lynn
LGI 1


Jill Manczka


CCIS


Jeff McCullough
LGI 2


LeeAnn McDowell
LGI 1


Bonnie Miller
LGI 1


Greg Merkle Conference Room A/B


Dennis Pack Conference Room A/B


Dianne Sederland Records Room


Cathy Shaw
LGI 1


Marlene Smith
LGI 1


Donna Volpe
LGI 1


Jim Warrender Conference Room A/B


Toby Woodward
Franklin



GROUP 2 Relocation

June 1, 2008


Nick Bernard
-

Calendar Completed


Nancy Breese
LGI 1


Paula Bredl


Calendar Completed


Judy Campagna
-

Calendar Completed


Denise Ferguson
LGI 2


Rhett Fertig
-

Calendar Completed


Carrie Fusco
LGI 1


Karen Gaggiano
LGI 1


Dan Gomola
LGI 2


Marilyn Goodrich
-

Calendar Completed


Karen Griffiths
LGI 1


Lorinda Hess
LGI 2


Marilyn Hillard
LGI 1


Tina Keller
-

Calendar Completed


Liz Kingsley
119


Wendy Kinnear
LGI 2


Ruth Klingensmith
LGI 1


Pat Kriley
LGI 2


Jane Martin
LGI 2


Carolyn Moore
LGI 1


Becky Moore
LGI 1


Gail Myers
LGI 1


Elaine Nagel
LGI 2


Kim Nicklin
LGI 1


Rosemarie Perrotta
LGI 2


Scott Powner Computer Lab


Nancy Richter
-

Calendar Completed


Lois Roach
LGI 1


Kim Zippie
LGI 2


GROUP 3 Relocation

July 1, 2008


Robert Barber 102


Dawn Book Computer Lab


Frank Cloud 103


Ken Davis Computer Lab


Kathy Fox 101


April Kisamore Computer Lab


Shelly Kyko Computer Lab


Sandra Masson 102


Crystal McFeely 103


Kathleen Molsky Computer Lab


Candi Surrena Computer Lab


Janine Welton Computer Lab


Laura Urbach 100A


Cecelia Yauger 100A



Questions

REMEMBER….THE FUTURE IS NOW!!!!!

MINOR INCONVENIENCE…..

MAJOR IMPROVEMENT!!!!


POWERPOINT WILL BE AVAILABLE ON
THE WEBSITE AND ELECTRONICALY
PER REQUEST


THANK YOU……QUESTIONS???