We hereby submit our proposal for the above referenced project based on our walk through with Marcel Perez-Pirio, architectural drawings prepared by Lacina Heitler dated 4/15/11, MEP drawings prepared by Tan Engineering dated 3/15/11 and addendum #1 dated 4/28/11 as described below:

alligatorsavoryΠολεοδομικά Έργα

26 Νοε 2013 (πριν από 3 χρόνια και 9 μήνες)

120 εμφανίσεις

We hereby submit our proposal for the above referenced project based on our walk through with Marcel

Perez
-
Pirio, architectural drawings prepared by Lacina Heitler dated 4/15/11, MEP drawings prepared by

Tan Engineering dated 3/15/11 and addendum #1 dated

4/28/11 as described below:

GENERAL CONDITIONS:

Provide full time supervision throughout the course of construction as necessary

Provide labor and materials to properly protect all adjacent spaces utilized by trades throughout the

course of construction a
s necessary

Provide labor and materials to properly protect all finish products installed by the various trades

throughout the course of construction

Provide labor to accept delivery, unpack & set in place all owner supplied furniture

DEMOLITION:

Demo all
existing interior walls

Demo interior doors, frames & trim

Demo existing furnishings, casework, desks, filing cabinets, counters, etc

Demo existing acoustical ceilings

Demo existing drywall ceilings

Demo existing VCT flooring

Demo exisiting built up plywoo
d flooring w/ VCT finish

Demo existing storefront entrance

Demo existing awning and metal support structure

Remove and cart all plumbing fixtures (8) sinks (2) toilet

Remove and cart existing radiator

Removal and carting of all light fixtures, conduit & wi
ring

Removal and carting of all ductwork (149 l/f) (26 S/R) (1 EF) (1 Heater)

Open sections of demising wall @ (6) locations between tennant and hallway to determine wall

construction

Provide mini containers for debris removal during demo

Provide mini
containers for debris during construction

STRUCTURAL STEEL:

Furnish & install steel supports welded to existing structural beams to support new AC
-
1

Furnish & install steel supports on exterior masonry wall to support new ACC
-
1

CONCRETE:

Furnish and instal
l concrete housekeeping pad for electric water heater

Patch back concrete beam bottoms after installation of supports for AC
-
1

Chop beam pockets for steel support of AC
-
1

CARPENTRY:

Type #1 Partition
-

Furnish & install 3 5/8"x 20ga mtl studs 16" o.c. slab
to slab with (1) layer 5/8" gyp

board each side to slab w/ top slip track 3" sound attenuation blankets and acoustic sealant @ floor slab

Type #1A Partition
-

Furnish & install 3 5/8"x 20ga mtl studs 16" o.c. slab to slab with (1) layer 5/8" gyp

board one s
ide only to 6" AHC w/ top slip track and acoustic sealant @ floor slab

Type #1C Partition
-

Furnish and install Double 3 5/8" mtl studs 16" o.c. slab to slab with (1) layer 5/8"

gyp board each side to 6" AHC with top slip track and acoustical sealant @ floo
r slab

Furnish & install (2) 3'x8'x24"thick drywall trimmed openings in Type 1C Partition

Type #2 Partition
-

Furnish & install 3 5/8" mtl studs 16" o.c. slab to slab with (1) layer 5/8" gyp board

each side to slab above with top slip track, 3" sound attenu
ation blankets and acoustic sealant @ floor

slab

Type #2A Partition
-

Furnish & install Double 1 5/8" mtl studs 16" o.c. slab to slab with (1) layer 5/8"

gyp board each side to slab above with top slip track, 3" sound attenuation blankets and acoustic seala
nt

@ floor slab for pocket door installation

Open wall, install blocking, patch wall @ (2) grab bars

Open wall, install blocking, patch wall @ (3) shelves in wash room

Open wall, install blocking, patch wall @ (10) station mirrors

Patch back demising walls

@ (6) locations opened during demo to determine wall construction. Tape &

polish to make ready for new finishes

Allowance to fire stop all existing upper slab penetrations w/ mineral wool and non
-
hardening caulk

Furnish & install plywood sub tops for
marble counters

Alternate MILLWORK:

Furnish & install all wood doors, jambs & hardware tag #2,3,4,5,6

Alternate MILLWORK:

Furnish & install millwork trimmed openings @ hair bar

Alternate MILLWORK:

Furnish & install millwork column surround @ window

Alterna
te MILLWORK:

Furnish & install millwork window seat

Alternate MILLWORK:

Furnish & install all crown, picture rail & base moldings

SPECIALTIES & ACCESSORIES:

Hang (10) station mirrors. (FBO)

Install large lounge mirror. (FBO)

Assemble & hang dbl. sided chal
k board (FBO)

Furnish & install 1/8" mdf panel mounted to single sided chalkboard sign and hang. Sign (FBO)

Furnish & install (2) grab bars.

Furnish & install (1) Kholer K11414 Robe Hooks

Furnish & install (1) Kholer K11415 Tissue Holder

Furnish & install
(1) Bobrick B221 Toilet Cover Disp

CEILINGS:

CT
-
1 Furnish & install Armstrong Ledges #8013 flush tegular tile with 9/16" superfine XL grid

CT
-
3 Furnish & install Armstrong Dune flat #1775 tile with 9/16' superfine XL grid

Gyp Clg
-

Furnish & install (1) lay
er 5/8" gyp board over 7/8" furring channel supported by 1 1/2"

channels. Tape and polish to make ready for new paint finishes

Furnish & insall gyp board soffits and fascias

Furnish & install 3" batt insulation above gypsum board ceilings & soffits

PAINTING:

Prep, prime and finish paint all gyp board ceilings

Prep, prime and finish paint all gyp board soffits & fascias

Prep, prime and finish paint all new and existing gyp board wall surfaces

Paint accent wall P
-
4

Paint pantry feature wall P
-
12 Dry Er
ase

Prep & finish paint all wood crown, picture rail & base

Prep & finish paint all wood doors & casing

Prep & finish paint column surround @ storefront

Prep & finish paint trimmed openings @ hair bar

Prep & finish paint window seat

Paint (1) chandelier in

washroom P
-
7 Highlight (FBO)

Paint (3) talbes P
-
7 Highlight (FBO)

Paint (1) mirror frame (FBO) P
-
7 Highlight in bathroom

Paint frame of (1) mirrors in waiting area

Paint double sided chalk board & frame

Paint single sided chalkboard sign & frame

Paint Aze
k panels @ storefront façade

Note:

-

Color and sheen as per plans & specs

-

Painting is assumed to be one color for the exception of the ceilings

-

All work to be done on straight time unless otherwise specified

-

Paint to be applied by roll
-
on and brush m
ethod




WALLCOVERING & FABRIC PANELS:

Furnish & install WF
-
4 Phillip Jeffries Quited Laquer 4555 Drama

Furnish & install WF
-
3 Carnegie silhouette
-
Embroidered 6271
-
103

Furnish & install (4) WF
-
2 Kravet

Fabric 30125 Tufted panels w/ white muslin backing and 1/2" poly

batting and 1/2" dia fabric buttons in 6x6 diamond pattern

Furnish & install (15) WF
-
1 Kravet Fabric 30125 panels w/ white muslin backing and 1/2" poly batting

FLOORING:

Furnish & install (1
) layer of 3/4" plywood subfloor underlayment @ all new scheduled flooring

installations

Furnish & install European Oak " San Tropez" pre
-
finished flooring. 5/8"x7.5x3'&6' lengths

Furnish & install Armstrong #5750 Naugat VCT

Furnish & install wood transiti
on thresholds to match W
-
1 floor finish @ all dissimilar materials

STONE:

Furnish and install Carrara White Honed stone tops w/ Stonetech bublletproof sealer or equal as per

plans & specs

Reception counter exterior

Reception counter interior

Back hair bar
display

Hair bar

Private hair bar

Prep tops with (60) 2" holes for gromets & iron cups

STOREFRONT CARPENTRY:

Furnish & install Azek panels on exterior storefront

Furnish & install (1) layer of 1/2" F.R.exterior plywood sheathing w/ vapor barrier, flashing
& caulking

@ Azek beadboard façade

Furnish & install plywood barricade for phase 2 storefront scope of work

STOREFRONT AWNING:

Allowance to Furnish & install new canvas awning on existing frame over residential entrance

STOREFRONT GLAZING:

Furnish &

install (1) 58" x 96" pair of 5/8" Starfire herculite doors w/ (1) 36" active leaf & (1) 22"

inactive leaf with 10" brushed stainless steel bottom rails, 24" ladder pulls & Dorma concealed door

closers

Replace all existing storefront glass in existing fra
mes to remain with 1/4" clear laminated safety glass

INTERIOR GLASS & MIRRORS:

Furnish & install 1/2" etched tempered glass in door #5

Furnish & install all 1/2" clear tempered safety glass shelving in millwork displays

Furnish & install all 1/4" clear mir
ror panels in hair bar, private hair bar, and individual display units

APPLIANCES:

Furnish & install GE Refrigerator GTR10HAXRWW

Furnish & install GE Dishwasher GSM1800NWW

Furnish & install U
-
Line Ice Maker B198

Furnish & install Summit UC Refrigerator CT6
6

ELECTRICAL:

Provide temp light and power

Disconnect power to all light fixtures scheduled to be removed

Disconnect power to all devices located in walls to be removed

Disconnect power to unit heater and exhaust fan

Disconnect and remove all obsolete bran
ch circuit conduit, boxes and wiring back to point of origin

Disconnect and remove 200amp switch, meter, feeder & panelboards

Tap existing service & install new 400amp fused switch

Furnish & install new 400amp meter w/ current transformer cabinet

Furnish &

install new 400amp service from disconnect to panel RP
-
1

Furnish & install 400amp 120/208 (2) section 84 circuit panel RP
-
1

Furnish & install Asco #918 120v multi pole relay w/ (6) contacts in Nema 1 enclosure for lighting

circuits

Furnish & install Tork

time clock with LED readout and manual over ride

Furnish & install remote 3 position momentary contact over ride switch tied into time clock for lighting

circuits

Extend existing circuits from 10 ton AC unit and Duct Heater to new panel RP
-
1

Furnish & ins
tall motor controller and power to ACC
-
1

Furnish & install motor controller and power to AC
-
1

Provide power & disconnect to pump CP
-
1

Provide power to motorized damper

Provide power & disconnect to electric water heater

Provide power & disconnect to new el
ectric duct heater

Provide power & disconnect to TX
-
A via Tork time clock

Furnish & install Wiremold G4000 series raceway 2 hair bar millwork

Provide power to ice maker, refrigerators, dishwasher

Furnish & install all light fixtures per plans, specs & sche
dule including: recessed down lights, wall

washers, pendants, sconces, cabinet, exits, emergency & exterior fixtures

Furnish & install all general purpose and dedicated devices & cover plates

Furnish & install roughing and Cat6 cabling for all tel/data dev
ices. Terminations & devices by others

Provide permits & all Building Dept sign offs

MECHANICAL:

Disconnect and drop all ductwork, S&R grilles, unit heater and exhaust fan scheduled for demo

Furnish & install new ACC
-
1

Furnish & install new AC
-
1 with conde
nsate pump & drip pan above ceiling in storage room

Furnish & install all refrigerant piping between ACC
-
1 and AC
-
1

Furnish & install 1" condensate drain line from CP
-
1 to nearest floor sink

Furnish & install TX
-
A and connect to existing louver @ rear of
store

Furnish & install FD @ extg toilet exhaust louver. Blank off unused portion of louver

Furnish & install motorized damper on fresh air duct to interlock with A/C unit operation

Furnish & install all new supply air ductwork from AC
-
2

Furnish & install
all new supply air ductwork from AC
-
1

Furnish & install all new supply outlets and R/A grilles

Clean and refurbish existing electric duct heater

Furnish & install (2) new thermostats

Furnish & install EHC for AC
-
1

Extg 10 ton unit to be cleaned and checked

for proper operation. Provide report of any dificiencies

Furnish & terminate all AC controls as required for complete installation & operation of AC
-
1 & AC
-
2

Insulate all ductwork and piping as per plans & specs

Provide shop drawings & balancing report

PL
UMBING:

Disconnect and remove all existing plumbing fixtures scheduled for demo

Remove all piping from existing fixtures back to mains

Installation only of (6) Owner Furnished Washroom Sink & Faucet

Furnish & install (6) Zurn model # 1175 hair interceptors

for wash room sinks

Furnish & install (1) Bar Sink & Faucet in pantry

Furnish & install (1) Lavatory Sink & Faucet

Furnish & install (1) Water closet & seat

Furnish & install electric water heater w/ expansion tank

Furnish & install all water, drain pipin
g and final connections for Refrigerator, Ice Maker & Dishwasher

as per manufacturers specifications

Furnish & install all required water, waste & vent piping for all plumbing fixtures as per plans & specs

Provide permits & all Building Dept sign offs

SPRI
NKLER:

Disconnect and remove (20) existing heads and associated piping scheduled to be relocated

Furnish & install (22) new heads with all associated piping, fittings, and hangers per plans & specs

Provide hydraulic calculations & shop drawings

Hydrostatically test system @ 200psi for 2 hours

Provide permit and all necessary Building Dept sign offs

Provide As Built drawings

CLARIFICATIONS & EXCLUSIONS:

-
All work to be performed by skilled open shop non
-
union labor

-
All work to be performed during

normal business hours

-
Any and all building related fees for engineers, elevator operators, security personnel or other building

related staff is excluded

-
All DOB filing and fees by others

-
We have included fees for picking up of permits

-
It is assumed t
hat the existing electrical service is without violation

-
We exclude handling & removal of any hazardous materials of any kind