TRIAD REPORT


A/E SERVICES


TABLE OF CONTENTS


NEW FACILITY PROJECTS

................................
................................
................................
.............................

2

Center for Tranformational Learning

................................
................................
................................
......

2

Forensic Science Institute

................................
................................
................................
.......................

2

Old North Renovation and Addition

................................
................................
................................
.......

2

FINE ARTS AND DESIGN

................................
................................
................................
..............................

2

Academy of Contemporary Music 2nd Floor Renovation

................................
................................
......

2

Melton Museum Remodel

................................
................................
................................
......................

2

Mitchell Hall West Lawn and Entry Walks

................................
................................
..............................

3

ATHLETICS

................................
................................
................................
................................
...................

3

Wantland Stadium Turf Replacement
................................
................................
................................
.....

3

Relocation of Fencing Southeast Side of Wantland Stadium

................................
................................
.

3

BUSINESS ADMINISTRATION

................................
................................
................................
.......................

4

Busine
ss Administration Building Roof Replacement & Repairs

................................
............................

4

COMMUNICATIONS BUILDING

................................
................................
................................
...................

4

School of Criminal Justice New Offices

................................
................................
................................
...

4

NIGH
UNIVERSITY CENTER

................................
................................
................................
..........................

4

NUC Room 224 Remodel (The Apple Store)

................................
................................
...........................

4

EXTERIOR CAMPUS IMPROVEMENTS

................................
................................
................................
.........

4

Jazz Lab Walk of Stars

................................
................................
................................
.............................

4

Lot 4 and Lot 6 Access Drive Changes

................................
................................
................................
.....

5

Main Street Resurfacing and Related Improvements

................................
................................
.............

5

WELLNESS AND STUDENT HEALTH

................................
................................
................................
.............

5

Rappel Tower Study

................................
................................
................................
................................

5

MATH AND SCIENCE

................................
................................
................................
................................
....

5

Coyner Hall Nursing Laboratory Improvements


Phase II

................................
................................
.....

5

Howell Hall Laboratory Building
-

Wet Specimen Addition

................................
................................
....

6

HOH Laboratory Remodel


Laboratory Classrooms 353 and 355

................................
.........................

6

Selman Learning Center Multi
-
Purpose Facility

................................
................................
......................

6

FACILITIES REPAIR & MAINTENANCE PROJECTS

................................
................................
.........................

6

Evans Hall Exterior Cast Stone Repairs

................................
................................
................................
...

6

Thatcher Hall Roof Replacement

................................
................................
................................
............

7

MISCELLANEOUS PROJECTS

................................
................................
................................
........................

7

Belva Howard Plaque

................................
................................
................................
..............................

7

Business Administratio
n Building Improvements Fund Raising Package

................................
...............

7

Business Administration Building Unisex Restroom (Rm. 102)
................................
..............................

7

Evans Hall West Exterior Stair

................................
................................
................................
.................

7

Fine Arts & Design Masterplan

................................
................................
................................
...............

7

Howell Hall Rm. 110 Laboratory Changes (proposed Bio
-
Mechanical Lab)

................................
...........

7

Howell Hall Rm. 208

................................
................................
................................
................................

7

Howell Hall Exterior


Isolated Areas of Cracking and Flaking of Brick Veneer on the 1962 Addition

...

7

Math & Science Masterplan
................................
................................
................................
....................

8

Melton Museum Wayfinding

................................
................................
................................
..................

8

Mitc
hell Hall Lobby and Entrance Lighting and Concession Counter

................................
.....................

8

Murdaugh Hall Plaza Stair

................................
................................
................................
.......................

8

Murdaugh Hall Plaza Deck Repairs

................................
................................
................................
.........

8

Nigh University Center Ballroom Remodel Concept

................................
................................
...............

8

Nigh University Center Rm. 317D


Academic Affai
rs

................................
................................
............

8

Nigh University Center Welcome Desk Interiors Improvements

................................
...........................

8

Testing Services in Thatcher Hall

................................
................................
................................
............

8

PROJECTS ON HOLD

................................
................................
................................
................................
....

9

Career Services (University Center


Rm. 338E)

................................
................................
.....................

9

Nigh University Center Counseling Center

................................
................................
.............................

9

Center for Volunteer & Service Learning (University Center


Rm. 212)


Director’s Office

.................

9


2

TRIAD REPORT












NEW FACILITY

PROJECTS


C
enter for Tranformational

Learning


AES Contact:

Kevin Tero/Bill Ewing


Current Status:

Occupants are moving into the building. Training is ongoing. The landscaping

is
scheduled
to be complete by July 3
1
th
.

Final punch list items remain for contractor to
complete.


Looking

Ahead:


The building needs to be cleaned again. Keys need to be issued to all those
requiring access.
The project needs to be closed out by A&E Services.


Additional Comment:


____________________________________________________________________________________


Forensic Science Institute


AES Contact:

Kevin Tero/Bill Ewing


Current Status:

The requisition for the final landscaping piece was requested July 29. The
land
scaping will be complete by August 20.


Looking Ahead:


The

final pay application is scheduled for approval and processing in July
.




Additional Comment:





Old North Renovation and Addition


AES Contact:

Kevin Tero/Bill Ewing


Current Status:
The grade beams for the
addition
have been
completed. Excavation for
utilities in the building footprint is being done by hand to avoid damage to existing utilities.



Looking Ahead:


The basement walls will b
e poured by August 13 and the basement will then
be backfilled.


Additional Comment:






FINE ARTS AND DESIGN


Academy of Contemporary Music
2nd

Floor Renovation



AES Contact:


Kevin Tero


Current Status:

Construction is underway. Demolition
is complete and the framing of new
walls has begun.

Work is on schedule.


Looking Ahead
:

The construction schedule shows occupancy in mid
-
October.


Additional Comment








Melton Museum Remodel


3

TRIAD REPORT







No Photo




AES Contact:

Rainey High

/ Adelina Jaha


Current
Status:

The minimum scope of thi
s project includes changes

to the electri
cal
distribution systems serving

this space

to meet code
. The
project
scope
may be increased to

include
partitions for
a classroom,
new ceiling
s

with new lighting, new partitions,
new flooring,
and more. AES, Physical Plant and Patco are currently evaluating the scope of electrical work
n
eeded to meet code. Fine Arts and Design has approved a floor

plan

for the new classroom
.


Looking Ahead:

AES will provide a schematic level e
stimate.



Additional Comment:


If
funding is identified to fund a project scope in excess of $50,000,

AES will request approval at RUSO.



Mitchell Hall West Lawn and Entry Walks


AES Contact:

Rainey High


Current Status:


Physical Plant has
completed

installation of site drainage
on north side of
Mitchell Hall, and replaced the lampposts.

Some shrubs and trees removed for the Howell Hall
Wet Specimen were moved to the west lawn at Mitchell.

A
new piece of sculpture
to be
installed in this ar
ea has been purchased by the President’s Office.


Looking Ahead:


Diversified
will install
the
bench pads

and donor
benches

in mid
-

to late
-

August
.
Irrigation
wi
ll start in late August or early September,

followed by landscaping
.



Additional Comment
:




A
THLETICS


Wantland Stadium Turf Replacement



AES Contact:


David Stapleton


Current Status:

This project entails

new artificial turf
installed
for
the 2011 football s
eason.

A & E Services will

endeavor
to deliver the project as much below budget ($1.2M) as possible
by
consider
ing

multiple
options
.
A & E Services has

received a
proposal
from
360
Architects,
the
firm that designed the football

stadium and original turf.

A PO will be issued as soon as
po
ssible, with the goal to

have
con
tract documents
ready

by
August 31
.
Bid Advertisement

will be
scheduled

pending decisions on use of turf for soccer, inlaid football stripes or not. Bid
timing will allow for

t
urf
installation
to
start in Feb. or March 20
11 and
complete June 1, 2011
.


Looking Ahead:


A & E
Services

and 360 Architects will

review multiple options for
replacement of the artificial turf
and then present
recommendations to

the Administration
.
Bidding documents may contain multiple
alternates
for costing and selection options.


Additional Comment:


Existing t
urf will be used
during the
FY 10 seasons.


_____________________________________________________________________________


Relocation of Fencing Southeast Side of Wantland Sta
dium



AES Contact:


David Stapleton / Bill Ewing


Current Status:

Formwork and rebar has been installed for t
he
new sidewalks; the concrete
pour for the sidewalks is scheduled on

July 30. The project is on schedule.


Looking Ahead:


Screen fencing
will start the week of August 2 and be complete the week of
August 13. The sidewalk outside the stadium is scheduled to be finished by August 13.
August
16 is the scheduled delivery date for the s
olid side fencing
.

Installation will follow
immediately

a
nd be complete before August 28.


Additional Comment:



_____________________________________________________________________________

4

TRIAD REPORT
















No Image Provided







No Image Provided

BUSINESS

A
DMINISTRATION


Business Administration Building Roof Replacement & Repairs


AES Contact:

Rainey High


Current Status:


A & E Services has received and reviewed

100

percent construction
documents
. A
n alternate to remove the existing cementi
tious insulation is needed. A & E
Services
will ask GSB to provide a fee to produce the alternate
.


Looking Ahead:


Bidding
has been re
schedu
led for October

2010
.


Additional Comment:


The p
roject budget is $550,000
(
FY 10 Section 13/Offset funds).


____________________________________________________________________________________


COMMUNICATIONS BUILDING


School of Criminal Justice New Offices


AES Contact:

Rainey High


Current Status:

This project entails remodeling office and classroom space on the first floor of
the Communications Building to serve as new offices for the School of Criminal Justice. A & E
Services is preparing a detailed description of the project to be submitted to
the CP3O
committee.


Looking Ahead:

This project

will be submitted to RUSO at the September meeting.


The work
is tentatively scheduled to start during winter break and reach completion by the end of
January.


Additional Comment:



____________________________________________________________________________________


N
IGH UNIVERSITY CENTER


NUC Room 224 Remodel (The Apple Store)


AES Contact:

Kevin Tero


Current Status:

T
he Nigh University Center

staff is installing drywall.


Looking Ahead
:

The Nigh University Center staff hopes to have the project complete by Aug.
16
th
.



Additional Comment

I/T department ha
ve

requested changes to the project and have gone
directly to the NUC staff and Purchasing department for these changes.







EXTERIOR CAMPUS IMPROVEMENTS




Jazz Lab Walk of Stars


AES Contact:

Rainey High


Current Status:

Th
is

project will add four new “Stars” to the

Walk of Stars
.


Looking Ahead
:


S
hop drawings

have been
approved, and fabrication of the bronze pieces is
underway.


A & E Services has extended the completion date to September 1

to account for
delays beyond th
e contractor’s control.


Additional Comment:


5

TRIAD REPORT













Photo here




____________________________________________________________________________________


Lot 4 and Lot 6 Access Drive Changes


AES Contact:


Rainey High


Current Status:

This
project
was approved by
RU
SO at the January
2010
meeting
. Funding
was provided in February to hire Wallace Engineering to make recommendations for the scope
of work.
On March 12
th
,
Wallace met with
A & E Services
,
the College of Business,
the
College
of Liberal Arts
,

and Transportation and Parking
Services

to hear about the
crowded and unsafe
conditions
ve
hicle users and pedestrians

face
circulating through and around these parking lot.


Looking Ahead:


At the request of Transp
ortation and Parking, Wallace has provided a fee
for a
traffic study
to
be used to justify a request to the City

of Edmond

to provide stop signs on
Bauman or
Ayers. The study will also
help
Wallace

redesign the lots to reduce the circulation
problems.


Additional Comment:


Transportation and Parking has decided to
postpone
the traffic stud
y
until the beginning of the 2010 fall semester. The construction is now scheduled for the

s
ummer
of
2011.

____________________________________________________________________________________




Main Street Resurfacing and Related Improvements


AES Contact:


Rainey High


Current Status
:

The General Contractor is Diversified Construction, with Connelly

Paving doing
the curb and paving work.
Project construction is
about
nearing completion
.
Remain
ing work
includes completion of the handrails and signage, and punch list work.



Looking Ahead:

This project will

be complete before

Aug. 13th




Additional

Comment:




____________________________________________________________________________________


W
ELLNESS AND STUDENT HEALTH


Rappel Tower Study


AES Contact:


Georgia Morgan & Rainey High


Current Status:

T
he rappel tower consult
ant
provide
d

a prelimina
ry review of the tower on
March 25, and initial estimates for corrections were provided by Diversified Construction of
Oklahoma, Inc., also on March 25.




Looking Ahead:



A report is due from Wellne
ss and Student Health that will:
1) outlin
e steps
to

be taken to address the corrections

recommended in the

March 25th document
, and 2)
provide a usage plan for the tower designed by a ROTC Mast
er C
limber.



Additional Comment:





MATH AND SCIENCE


Coyner Hall Nursing
Laboratory Improvements


Phase II


AES Contact:

Rainey High


Current Status:

Diversified and Matrix are partnering to find the most cost effective materials
and systems appropriate for this project. Once this effort is over, Matrix will complete the
do
cuments.


Looking Ahead:


This project
has been rescheduled to start
in
late
August
.


Additional Comment:


6

TRIAD REPORT





here






Photo here






Photo here






Photo here

____________________________________________________________________________________


Howell Hall Laboratory Building
-

Wet Specimen Addition


AES Contact:


Rainey High


Current Status
:


The foundation work is underway
.



Looking Ahead:





Additional Comment
:


Construction meetings are scheduled for every other Wednesday at
3:15 in the Math and Science Dean’s Conference
Room.


_____________________________________________________________________________


HOH Laboratory Remodel



Laboratory Classrooms 353 and 355


AES Contact:


Rainey High


Current Status:


This project is 90 percent complete and will reach substantial completion by
August
9
.


Looking Ahead:


Phase two is scheduled for Christmas break
.


Additional Comment:

During the design process in March, Matrix, with JCI’s assistance,
determined that

the existing building make
-
up air is not sufficient to support additional hoods.
This
led to the request to RUSO to increase

project scope
.
Th
e increased
scope is too large to
complete thi
s summer, so A & E Services
divided the project int
o two phases
.

_____________________________________________________________________________


Selman Learning Center Multi
-
Purpose Facility


AES Contact:


Rainey High


Current Status:

The exterior walls are complete
.

The

joists and steel deck have been
installed. Concrete
placement on the metal roof deck is scheduled for August 6.


Looking Ahead:



On August 9
, the contractor will start installation of metal studs, followed by
electrical and plumbing rough
-
in.
The campus Fire Marshal and A & E Service
will conduct
50
percent
building
inspection the week of August 16
.



Additional Comment:




FACILITIES REPAIR
& M
AINTENANCE PROJECTS


E
vans Hall Exterior Cast Stone

R
epairs


AES Contact:


Rainey

High


Current Status:



Meyer Plus submitted a
scoping report

on July 21.
On July 29,
A & E Services
requested changes to this report. These changes are due August 9, 2010.


Looking Ahead:



The
approved

bud
get
is

$300,000

from fiscal year 2010 funds

and $100,000
in FY 2011 funds
, for a total budget of $400,000.


Additional Comment:


Though
the available funds will
not
address
all needed repa
irs, they will
be applied by unit price basis according to the condition of the masonry (those areas most
ne
eding repair first) and should go a long way toward preserving the building.

Bidding is
tentatively scheduled for September

2010
.




7

TRIAD REPORT





Thatcher Hall Roof Replacement


AES Contact:


Kevin Tero


Current Status:


At the April meeting, RUSO approved Master
Lease funding for this

project
.
Funds will be available for construction in February/March 2011. The goal is completion of the
repair and replacement work
by

mid
-
August,
2011.


Looking Ahead:




Additional Comment
:



_____________________________________
________________________________________


M
ISCELLANEO
US

PROJECTS



This category includes

small
er

projects that
are below reporting limits.
These projects

are
relatively
low budget,
may be limited to planning

or preliminary design
,
and are either
currently underway or have been delayed
for some time
.


Belva Howard Plaque

Shop Drawings for the Belva Howard plaque have been submitted to A & E Services for
review
.
Project Contact:
Kevin Tero,
Rainey High

Business Administration
Building Improvements Fund Raising Package

The scope of this project
is limited to providing concepts and promotional material for

improvements to the Dean’s Suite.

Architectural firm KSQ has met with the dean and
will
provide these servic
es.


Architect
ural and Engineering Services and Environmental Health
and Safety will identify

potential code issues to

be addressed in KSQ’s scope

and
fee
.
Project

Contact: Kevin Tero

Business Administration Building Unisex Restroom

(Rm. 102)

This restroom is designa
ted as accessible, but falls short of ADAAG requirements and is
difficult for handicapped individuals to use. Business Administration and the campus code
compliance officer have asked AES to estimate the cost to bring the room up to code.
Project Contac
t: Rainey High

Evans Hall West Exterior Stair

While reviewing the condition of the cast stone and brick exterior at Evans Hall, Meyer Plus
Associates
observed
deterioration to the concrete structure supporting the west exterior
stair. A &

E Services will bring an structural engineer on site to advice how soon repairs are
needed, and to provide a fee for specifying the repairs.
Project Contact: Rainey High

Fine Arts & Design Masterplan

A & E Services will assist

the College of Fine Arts a
nd Design prepare a masterplan.
Project
Contact: Rainey High

Howell Hall Rm. 110 Laboratory Changes (proposed Bio
-
Mechanical Lab)

Equipment has been purchased to conduct bio
-
mechanical research that involves the use
of mice and bovine tissues classified as level 1 and possibly level 2 biohazards.
Environmental Health and Safety
has provided a list of req
uested improvements to the
r
oom
; Math and Science has submitted a list of Work Orders to Physical Plant.
Project
Contact:
Georgia Morgan /
Rainey High

Howell Hall Rm. 208

Math and Science has asked for preliminary design assistance to remodel the Dean’s
Office. Currently, the scope of the work will be limited to new carpet and paint and other
minor changes.
Rainey High

Howell Hall Exterior


Isolated Areas of Cracking an
d Flaking of Brick Veneer
on the 1962 Addition

On May 28, Physical Plant provided
the
new
personnel
lift

to provide a close look of the

problem. A & E Services and
Wallace Stru
ctural E
ngineer
s

provided reports to Physical
Plant on June 1.

Physical Plan
t has asked MidContinental to provide a price to repair this
area.

Project Contact: Rainey High

8

TRIAD REPORT



Math & Science
Masterplan

A & E Services

and EHS will help

the College of Math & Science prepare a masterplan
.


The
first step of this plan is the gathering of detailed information from Math & Science on
current laboratory functions, and the laboratory functions Math & Science intends to
develop in the future.
Project Contact: Rainey High

Melton Museum Wayfinding

A & E Services presented concepts
spring
2009
to the Dean for improved way

finding
signage leading to and identifying the Melton Art Gallery
.

This project is currently on hold
until sufficient staff time is available to move forward with development of t
he concepts.
Project Contact: Rainey High

Mitchell Hall Lobby and Entrance Lighting and Concession Counter

Theater Arts has budgeted
between
$5,000
and $9
,000
to construct a new Concessions
Counter and purchase new light fixtures

for the lobby areas. A
& E
Services

me
t with the
direc
tor of Mitchell Hall on March 25
th
.

The design

for this

project is tentatively scheduled
to be complete

by

August 1
.
Project Contact: Elspeth Brown

/ Rainey High
.

Murdaugh Hall Plaza Stair


Th
is project entails modification of the exterior concrete stair that leads up to the north
plaza deck. A & E
Services submitted drawings to EHS on May 10 which were permitted
May 12 and provided to Housing on May 14.


Due to safety concerns ab
out this stair, this
project has been added to the list of projects to be done this summer. Project Contact:
Rainey High

Murdaugh Hall Plaza Deck Repairs


Housing arranged for the removal of part of the Plaza Deck topping slabs the week of July
19 to enable Wallace
Engineers

and A & E Services to see the composition of the topping
and waterproofing membrane and preliminarily evaluate the condition of the
wat
erproofing and structural deck. There appears to be some degradation of the concrete
beam situated below the exterior lobby doors that exit onto the plaza. Wallace will further
investigate this and make recommendations for 1) temporary shoring (if needed
) and 2)
permanent repair. A & E Services will assist with recommendations for replacement of the
existing topping slab and installation of a functioning deck drainage and waterproofing
system.


Project Contact:
Darrell Stinchcomb /
Rainey High


Nigh Un
iversity Center Ballroom
Remodel
Concept

Auxiliary
Enterprises
previously asked
A & E Services

to develop a concept to
update the
ballroom lighting
, which was done. Then Auxiliary Enterprises requested concepts to
update the finishes in the ballroom. On
Feb.

26
th
,

A & E Services
, Glover
-
Smith
-
Bode, Jason
George Interior Design
,

and Diversified

Construction
of Oklahoma, Inc.
met with Auxiliary
Enterprises
to review concepts develope
d by
A & E Services

for economically remodeling
the ballroom.


Changes to t
he concept were proposed, and
Auxiliary

Enterprises

approved
moving forward with
developing these

change
s. At Auxiliary Enterprises’ request, a
package including elevations, artwork, and finishes will be developed to present to the
Administration and for

fund raising purposes.

Project Contact: Rainey High

Nigh University Center Rm. 317D


Academic Affairs

Rework of existing cubicles and new or reused additional cubicles are needed to
accommodate all employees of one department together. Project Contac
t: Elspeth Brown

Nigh University Center Welcome Desk Interiors Improvements

A & E Services is designing interiors improvements for the Welcome Desk at the main
entrance to the University Center. Contact: Elspeth Brown

Testing
Services

in Thatcher Hall

A partition and other minor
changes are needed in the testing facilities
to
comply with
national standards.

A & E Services

me
t with the client on February 2
6
th

to review the
desired
scope of
work.

Due to limited funds, improvements
to b
e made in the near future
will be of modest cost and aimed at reducing noise (curtains at windows, ceiling tile)
.


None of the changes planned in the future
include major changes to the use of or
configuration of the space
.


Project Contact: Rainey Hig
h





9

TRIAD REPORT















Photo here









PROJECTS ON HOLD


Career
Services

(University Center


Rm. 338E)


AES Contact:

Rainey High


Current Status:

This project is on hold pending administrative review of space utilization in the
University Center.


Looking Ahead:


The C3PO
Committee has reviewed space utilization

and has recommended
the modifications requested.


Additional Comment:


This project is on hold p
ending
approval by the Executive Committee.




Nigh University Center Counseling Center


AES
Contact:


Rainey High


Current Status:

T
his project has been placed on hold.


Looking Ahead:



Additional Comment
:



_____________________________________________________________________________


Center for Volunteer & Service Learning
(University Center


Rm. 212)


Director’s Office


AES Contact:

Rainey High


Current Status:

This project has been approved by the Executive Committee, however funding
for this project is currently unavailable. If and when funding is identified for this

project, the
project will be rescheduled
.


Looking Ahead:


A & E Services will contact Academic Affairs to see if and when funding will
be available.


Additional Comment:




_____________________________________________________________________________